It is impossible to pass Oracle 1Z0-567 exam without any help in the short term. Come to Actualtests soon and find the most advanced, correct and guaranteed Oracle 1Z0-567 practice questions. You will get a surprising result by our Renewal Primavera P6 Enterprise Project Portfolio Management 8 Essentials practice guides.
Check 1Z0-567 free dumps before getting the full version:
NEW QUESTION 1
Select the true statement regarding live or summarized data.
Answer: D
Explanation:
The Project Baseline is a single metric for comparison that enables all members of a team to have a shared and consistent set of data against which to evaluate project progress. There is only one Project Baseline at any time. All pages that display summarized data compare and display data against the Project Baseline.
Reference; P6 EPPM User's Guide, About Baselines
NEW QUESTION 2
Identify two ways of quickly creating templates.
Answer: AE
Explanation:
You can create a template from an existing project, create it from scratch, or create it from another template.
Note: Creating a new project template
As mentioned, you can either create a template from an existing project.
From the main menu, choose the Projects tab and click on the Add Project Template icon. You get the following page:
Where, Copy from existing project or template: Allows you to create a template based on an existing project or template.
NEW QUESTION 3
You are an executive that wants to review portfolio data for a high-risk/high-priority group of projects. You go to Portfolios in Primavera P6 Web. However, the data shown is not the correct portfolio. What should you do to correct this problem?
Answer: C
NEW QUESTION 4
Select the true statement regarding currencies.
Answer: A
Explanation:
The base currency is the monetary unit used to store cost data for all projects in the database and is controlled by a global administrative
setting in the Project Management module. The default base currency for Primavera is US dollars ($). The view currency is the monetary unit used to display cost data in Primavera and is controlled by a user preference.
Note: All costs are stored in the Based Currency. All costs are stored in the Base Currency and all other Currencies are calculated values using the Base Currency value and conversion rate.
NEW QUESTION 5
Identity the true statement regarding the Must Finish By constraint.
Answer: B
Explanation:
Must Finish date is not constraining Activity. It is used to calculate the schedule on "Backward pass" to show the float whether negative or positive. If Must finish date is less than current project finish date then some critical activities will be showing negative float but if current project finish date is less than must finish date then it will show all positive float.
Note: Primavera calculates the backward pass starting from the end date of the project finish date you enter manually. Therefore, if the end date is not possible to be achieved using the network logic that you have made, then you will always get negative total float
NEW QUESTION 6
Identify the true statement regarding currency preferences for viewing currency.
Answer: C
Explanation:
* User Preferences | Currency sets the currency to display in P6, as well as the type
of currency symbol and whether to show decimal places.
* My Preferences offers options for you to customize the data display format across all sections of P6. The options you customize are exclusively yours. You can alter global preferences, including formats for time units, dates, and currencies.
NEW QUESTION 7
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You want to create s global activity view that includes a filter to show only activities that have required work products and documents as per the methodology. Identify three actions that would help you to accomplish this.
Answer: ACE
Explanation:
Filter on the Global Activity Code and display in the activity view.
NEW QUESTION 8
When assigning a user to a user-interface view, deselecting the Allow Editing check box restricts the user’s ability to _____.
Answer: B
Explanation:
Creating User Interface Views
On the Create User Interface View page, click the Users tab:
Select a user from the Available Users window to assign the user to that view. Click Select to move the user to the Selected Users column.
Select the Allow Editing option to enable the user to edit the contents of their interface view.
Reference; P6 EPPM Administrator’s Guide, Creating User Interface Views
NEW QUESTION 9
Identify the true statement regarding a Capacity Planning chart.
Answer: A
Explanation:
Example of Capacity Planning chart:
Frame B is the top-right quarter of the Capacity Planning screen. This is the Gantt area where projects are represented using scheduled dates on the green bar. The orange bar is only seen in P6 on this screen and represents the forecast. The forecast bar will be the same as the schedule/current dates bar unless forecast dates are specifically used (which is not typical). The purpose of the two bars is best used
when viewing bids or projects in the future.
Note:
Using the Chart tab, users can change the Capacity Planning view to show Units or Costs in the Gantt chart, and can choose to display either only projects selected or the entire portfolio. Other adjustments can be made here to create a desired view.
NEW QUESTION 10
Identify one filter enhancement in P6 R8.
Answer: D
Explanation:
New in Release 8.2 include:
* Is Under filter: This is a new property used in filtering data which lets you filter by location of an item within a hierarchy. For example, you can filter for activities only under a certain WBS (Work Breakdown Structure) node. See figure below:
NEW QUESTION 11
Identify two benefits of customizing user-interface views.
Answer: AE
Explanation:
A: Define user interface views that restrict and provide access to P6 Web Access functionality according to the requirements of your
company’s functional roles.
E: Defining a prototype user
configuration, in combination with defining user interface views,
ensures that new users of P6 Web Access will have a consistent interface customized for the business needs of the organization.
Note:
* Privilege Edit User Interface Views:
Create, edit, and delete user interface views in P6 Web Access. This privilege also grants you the right to assign user interface views to users in both P6 Web Access and the Project Management module.
* In addition to licensing and security privileges, you can further control access to P6 Web Access functionality using user interface views. A user interface view is a defined set of tabs, pages, and Action Menu items that a user assigned to that view can access in each section of P6 Web Access (Dashboards, Portfolios, Projects, and Resources). You can create multiple user interface views that correspond to the job functions performed by each role in your organization, or you can create user interface views to meet each individual user's needs. User interface views can only be defined in P6 Web Access and can be assigned to users in both P6 Web Access and the Project Management module.
NEW QUESTION 12
You are working with a customer that has had Primavera P6 running in a global instance for four years the customer has asked you to come in and review the instance to identity opportunities for optimizing the system. As you look into the coding libraries, you see much duplication of project codes. You recommend that the customer come to consensus on the duplicate codes and values, and then eliminate the redundant codes.
What functionality should you utilize to minimize the potential disruption to the user base?
Answer: D
Explanation:
Note: Project Codes allow for grouping, sorting, and filtering projects. They are used extensively and allow you to organize your project in many ways, particularly for reporting and when performing portfolio analysis (See Chapter 11, Portfolios). Think of codes as categories or labels; they can be used individually or in combination to group or give totals for different categories in reports or portfolios.
Reference: Oracle Primavera P6, Assign, revise, or remove project codes
NEW QUESTION 13
Select two true statements regarding calendars.
Answer: BE
Explanation:
B: Project calendars can only be used within a specific project, and can be assigned to activities within the project. A project can also have a default
calendar, which may be either a project calendar or a global calendar.
E: A resource calendar is designed to work for a specific resource. Furthermore, calendars can be assigned to activities and to the resources assigned to that activity.
Note: Calendars describe the time available for project work. A calendar can be defined at three levels: global, project, and resource.
NEW QUESTION 14
Identify three types of activity codes.
Answer: ACD
Explanation:
Note: Global Activity Codes (but not Project-level or ESP-level) that may be created at any time and applied to any project.
NEW QUESTION 15
What is the process that must be followed by a system administrator to create a user?
Answer: B
NEW QUESTION 16
This graphic is an example of a ____.
Answer: D
Explanation:
Example:
Note the checkboxes to the left-hand side of each project. If you uncheck a box, then that project will be removed from the totals displayed. This will also remove that project from the accompanying portfolio view.
NEW QUESTION 17
You are a portfolio manager. You opened a portfolio and you refreshed the filter. However, some of the projects that were previously in the portfolio are no longer there.
What happened?
Answer: A
Explanation:
If you choose to update Primavera activities that fall within a filter and choose to add new activities, only activities that meet that filter’s criteria will be added.
NEW QUESTION 18
Where are risk response plans captured?
Answer: C
Explanation:
The Response Plans detail window is the area in the risk register where you create plans for handling the identified risks. Once you have identified which project risks need further action, create a response plan and assign response plan action items for each risk to reduce the negative impact on the project.
Example below:
Reference: Oracle Primavera P6, Working with Risk Response Plans
NEW QUESTION 19
Identify the business case that would support the creation of OBS elements to align with WBS elements within individual project plans.
Answer: C
Explanation:
A work breakdown structure (WBS) is a hierarchical arrangement of the products and services produced during and by a project. The project is the highest level of the WBS while an individual activity required to create a product or service is the lowest level. Each project in the enterprise project structure (EPS) has its own WBS.
When creating a project, the project manager typically develops the WBS first, assigns work products and documents to each WBS element, and then defines activities for performing the element’s work. Specific earned value calculations can be specified for each WBS element, along with an organizational breakdown structure (OBS) element responsible for all work included in the WBS element.
NEW QUESTION 20
What is the significance of setting "Summarize project based on high-level resource planning"?
Answer: A
Explanation:
Typically, use the High Level Resource Planning option for future projects that are currently planning only high-level resource allocation requirements, or for projects that are underway, but for which you do not want to assign resources at a detailed activity- level.
Note: ‘Summarize Project Based on’ determines whether the Summarizer calculates and displays rolled-up data based on resource assignments at the activity or project level.
Note 2: You can summarize project data to a specific WBS level when calculating and maintaining summary data.
NEW QUESTION 21
You are a project manager managing a large construction project. One of the pieces of heavy equipment required to dig the Foundation will most likely not be available until a specific date, because that equipment has been allocated to another, higher priority project. In that related project schedule you clearly see that in all likelihood, the activity in that plan that uses that equipment will also slip. You want to reflect this in your project schedule using a constraint.
What would be the most appropriate constraint to use?
Answer: C
Explanation:
Start On or After defines the earliest date an activity can begin. This constraint affects only early dates. When calculating a schedule, P6 Web Access imposes the start on or after constraint in the forward pass only if the calculated early start date will be earlier than the imposed date.
Note: Primary Constraint and Secondary Constraint can be applied to activities. The possible constraint types are:
• Start On
• Start On or Before
• Start On or After
• Finish On
• Finish On or Before
• Finish On or After
• As Late as Possible
• Mandatory Start
• Mandatory Finish
Reference: Oracle Primavera P6, Activity constraint types
NEW QUESTION 22
......
P.S. Certleader now are offering 100% pass ensure 1Z0-567 dumps! All 1Z0-567 exam questions have been updated with correct answers: https://www.certleader.com/1Z0-567-dumps.html (84 New Questions)