Theres a simple quite normal misunderstanding for the Cisco 200-125 examination accreditation that its a quite challenging style of accreditation for being achieved. However that is a thoroughly bogus suggestion. It merely requires the appropriate 200-125 research materials and youll be on your way toward results. Though there are lots of web-sites which will conduct this, most of them are frequently fake or unwanted. Consequently, be very careful also very important inside your range of your website.

2021 Sep 200-125 exam answers

Q91. - (Topic 2) 

Refer to the exhibit. 


A technician is troubleshooting host connectivity issues on the switches. The hosts in VLANs 10 and 15 on Sw11 are unable to communicate with hosts in the same VLANs on Sw12. Hosts in the Admin VLAN are able to communicate. The port-to-VLAN assignments are identical on the two switches. What could be the problem? 

A. The Fa0/1 port is not operational on one of the switches. 

B. The link connecting the switches has not been configured as a trunk. 

C. At least one port needs to be configured in VLAN 1 for VLANs 10 and 15 to be able to communicate. 

D. Port FastEthernet 0/1 needs to be configured as an access link on both switches. 

E. A router is required for hosts on SW11 in VLANs 10 and 15 to communicate with hosts in the same VLAN on Sw12. 

Answer: B 


Q92. - (Topic 3) 

Which IPv6 address is valid? 

A. 2001:0db8:0000:130F:0000:0000:08GC:140B 

B. 2001:0db8:0:130H::87C:140B 

C. 2031::130F::9C0:876A:130B 

D. 2031:0:130F::9C0:876A:130B 

Answer: D 


Q93. - (Topic 4) 

A router has learned three possible routes that could be used to reach a destination network. One route is from EIGRP and has a composite metric of 20514560. Another route is from OSPF with a metric of 782. The last is from RIPv2 and has a metric of 4. Which route or routes will the router install in the routing table? 

A. the OSPF route 

B. the EIGRP route 

C. the RIPv2 route 

D. all three routes 

E. the OSPF and RIPv2 routes 

Answer: B 


Q94. - (Topic 1) 

Refer to exhibit: 


Which destination addresses will be used by Host A to send data to Host C? (Choose two.) 

A. the IP address of Switch 1 

B. the MAC address of Switch 1 

C. the IP address of Host C D. the MAC address of Host C 

E. the IP address of the router's E0 interface 

F. the MAC address of the router's E0 interface 

Answer: C,F 


Q95. - (Topic 3) 

Which IPv6 address is the equivalent of the IPv4 interface loopback address 127.0.0.1? 

A. ::1 

B. :: 

C. 2000::/3 

D. 0::/10 

Answer: A 


200-125 free draindumps

Abreast of the times 200-125 exam answers:

Q96. - (Topic 9) 

If a router has four interfaces and each interface is connected to four switches, how many broadcast domains are present on the router? 

A. 1 

B. 2 

C. 4 

D. 8 

Answer: C 


Q97. - (Topic 7) 

Scenario 

Refer to the topology. Your company has decided to connect the main office with three other remote branch offices using point-to-point serial links. 

You are required to troubleshoot and resolve OSPF neighbor adjacency issues between the main office and the routers located in the remote branch offices. 









R1 does not form an OSPF neighbor adjacency with R2. Which option would fix the issue? 

A. R1 ethernetO/1 is shutdown. Configure no shutdown command. 

B. R1 ethernetO/1 configured with a non-default OSPF hello interval of 25: configure no ip ospf hello-interval 25 

C. R2 ethernetO/1 and R3 ethernetO/O are configured with a non-default OSPF hello interval of 25; configure no ip ospf hello-interval 25 

D. Enable OSPF for R1 ethernetO/1; configure ip ospf 1 area 0 command under ethernetO/1 

Answer: B 


Q98. - (Topic 8) 

The output of the show frame-relay pvc command shows "PVC STATUS = INACTIVE". What does this mean? 

A. The PVC is configured correctly and is operating normally, but no data packets have been detected for more than five minutes. 

B. The PVC is configured correctly, is operating normally, and is no longer actively seeking the address of the remote router. 

C. The PVC is configured correctly, is operating normally, and is waiting for interesting traffic to trigger a call to the remote router. 

D. The PVC is configured correctly on the local switch, but there is a problem on the remote end of the PVC. 

E. The PVC is not configured on the local switch. 

Answer: D 


Q99. - (Topic 2) 

Refer to the exhibit. 


Which statement is true? 

A. The Fa0/11 role confirms that SwitchA is the root bridge for VLAN 20. 

B. VLAN 20 is running the Per VLAN Spanning Tree Protocol. 

C. The MAC address of the root bridge is 0017.596d.1580. 

D. SwitchA is not the root bridge, because not all of the interface roles are designated. 

Answer: D 


Q100. - (Topic 7) 







Which will fix the issue and allow ONLY ping to work while keeping telnet disabled? 

A. Correctly assign an IP address to interface fa0/1. 

B. Change the ip access-group command on fa0/0 from "in* to "out. 

C. Remove access-group 106 in from interface fa0/0 and add access-group 115 in. 

D. Remove access-group 102 out from interface s0/0/0 and add access-group 114 in 

E. Remove access-group 106 in from interface fa0/0 and add access-group 104 in. 

Answer: E