Your success in Microsoft 70-348 is our sole target and we develop all our 70-348 braindumps in a way that facilitates the attainment of this target. Not only is our 70-348 study material the best you can find, it is also the most detailed and the most updated. 70-348 Practice Exams for Microsoft 70-348 are written to the highest standards of technical accuracy.

Q1. DRAG DROP

You are a project manager in an organization that is using Microsoft PPM. Some of your resources update their assignments correctly.

You need to accept their updates without review by setting up an approval rule.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

Answer:


Q2. DRAG DROP

You are the administrator for an organization that uses Microsoft PPM. Users must be able to create projects by using predefined templates.

You need to create a new Enterprise Project Template and make it available for users.

Answer:


Q3. You are a project manager using Microsoft PPM,

You need to create a new project that uses one of your company's templates.

What are two ways to achieve the goal? Each correct answer presents a complete solution.

A. From Microsoft Project, select Enterprise.

B. In Project Center, select New and then select the desired enterprise project type.

C. In Resource Center, select New.

D. From Microsoft Project select Featured.

Answer: A,B


Q4. You are project manager for an organization that is uses Microsoft PPM. You need to create a project deliverable for the current project. What should you do?

A. In Microsoft Project manage a deliverable.

B. On the project site, edit the list to include the Task ID attribute.

C. In Microsoft Project use Sync Deliverables,

D. On the project site, create a new item in the Deliverables list

Answer: A


Q5. HOTSPOT

You are a project manager and want to display key deliverables associated with your project The tasks that produce deliverables are already on the project schedule.

You need to ensure that the deliverables are visible on the project site.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.

Answer:


Q6. DRAG DROP

You are project manager in your company's PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.

You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer:


Q7. HOTSPOT

You create a new project plan. You plan to take a snapshot of the project before and after the project start date. For each of the following statements, select Yes if the statement is true. Otherwise, select No.

Answer:


Q8. You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost, Proposed Benefits, and Sponsor Name properties.

The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.

You need to use a project approval workflow.

Which three objects should you use? Each correct answer presents part of the solution.

A. Project Departments

B. Enterprise Project types

C. Project Detail Pages

D. Project schedule templates

E. Phases and stages

Answer: B,C,E


Q9. DRAG DROP

You are the Microsoft PPM administrator for a large organization.

You need to ensure that line managers can delegate timesheet approvals to their team members.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

Answer:


Q10. HOTSPOT

You are the project manager for a real estate management company. You are using Microsoft Project to manage the development of a new restaurant The schedule includes a task named Equipment delivery.

Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2021.

You need to modify the Equipment delivery task.

How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.

Answer: