Cause all that matters here is passing the Microsoft 70-414 exam. Cause all that you need is a high score of 70-414 Implementing an Advanced Server Infrastructure exam. The only one thing you need to do is downloading Examcollection 70-414 exam study guides now. We will not let you down with our money-back guarantee.
Q111. - (Topic 1)
You need to recommend a solution for managing updates. The solution must meet the technical requirements.
What should you include in the recommendation?
A. A System Center 2012 Configuration Manager management point in the main office and a WSUS downstream server in each office
B. A System Center 2012 Configuration Manager software update point in the main office and a System Center 2012 Configuration Manager distribution point in each office
C. A System Center 2012 Configuration Manager management point in the main office and a System Center 2012 Configuration Manager distribution point in each office
D. A WSUS upstream server in the main office and a WSUS downstream server in each office
Answer: B
Q112. - (Topic 2)
You need to recommend changes to the existing environment to meet the email requirement.
What should you recommend?
A. Implement a two-way forest trust that has selective authentication.
B. Implement qualified subordination.
C. Deploy the FabrikamCA root certificate to all of the client computers.
D. Deploy a user certificate from FabrikamCA to all of the users.
Answer: B
Q113. - (Topic 7)
You need to automatically restart the appropriate web service on DETCRL01 and CHICRL01 if the web service is stopped.
Solution: You create a recovery task in SCOM and configure it to start the World Wide Web publishing service.
Does this meet the goal?
A. Yes
B. No
Answer: A
Q114. - (Topic 3)
You need to recommend a monitoring solution for Northwind Traders.
What is the best approach to achieve the goal? More than one answer choice may achieve the goal. Select the BEST answer.
A. Three Operations Manager management servers and two Operations Manager gateway servers
B. One Operations Manager management server
C. Two Operations Manager management servers and three Operations Manager gateway servers
D. Five Operations Manager management servers
Answer: C
Q115. - (Topic 8)
Your company has a main office and a branch office.
You plan to implement a failover cluster named Cluster1 to host an application named App1. The data of App1 will replicate to all of the nodes in Cluster1.
Cluster1 will contain two servers. The servers will be configured as shown in the following table.
The cluster nodes will not use shared storage.
The branch office contains two file servers named Server3 and Server4.
You need to ensure that App1 fails over automatically to another server if a single node in Cluster1 fails.
What should you do?
More than one answer choice may achieve the goal. Select the BEST answer.
A. Add Server3 as a node in Cluster1.
B. Add Server1, Server2, and Server3 to a Network Load Balancing (NLB) cluster.
C. Add Server3 and Server4 to a new failover cluster named Cluster2. Install App1 on Cluster2.
D. Add Server3 as a file share witness for Cluster1.
Answer: D
Q116. - (Topic 8)
Your network contains an Active Directory domain named contoso.com. The domain contains a Microsoft System Center 2012 infrastructure.
You deploy a service named Service1 by using a service template. Service1 contains two virtual machines. The virtual machines are configured as shown in the following table.
You need to recommend a monitoring solution to ensure that an administrator can review the availability information of Service1.
Solution: From Configuration Manager, you create a Collection and a Desired Configuration Management baseline.
Does this meet the goal?
A. Yes
B. No
Answer: B