When you convey a Microsoft 70-498 recognition in your experience, it can initial help you through helping replace your get the job done stream. By advancing your knowledge bottom, you have much better comprehension of your work and be able to get the job done extra expeditiously. More, you can find out your way within the software programs superior to a good number of, that should usually help you look for the fastest and a lot of effective opportinity for one to attain the assignments. But that doesn?¡¥t purely close having very own work productivity ranges and also recognizing virtually all you should know pertaining to Microsoft solutions.
Q21. You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint.
You need to conduct a retrospective meeting prior to planning the next sprint.
What should you do?
A. Analyze and revise the story points of the work items completed in the previous sprint.
B. Analyze the previous sprint to identify what the team is going to do differently during the next sprint.
C. Analyze items in the product backlog for the next sprint.
D. Determine which items have been finished on the previous sprint.
Answer: C
Q22. You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process template.
You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to complete the sprint.
You need to ensure that the agreed upon work is assigned to team members. Who should be responsible for assigning work to team members?
A. Team members
B. Product owner
C. Scrum master
D. Team lead
Answer: A
Explanation: In Scrum, work should never be directed or assigned. When creating or updating a task, don’t assign it to anyone who doesn’t request the work.
Professional Scrum Development with Microsoft Visual Studio 2012 p.183
Q23. You develop an n-tier application that includes the following components:
Database
Data access layer
Business logic layer
Presentation layer (website)
The database has approximately 100 tables and stores large amounts of data.
You need to select a unit testing strategy to verify the business logic layer.
What should you do?
A. . Create a mock data access layer.
. Configure the business logic layer to use the mock data access layer.
. Write tests against the business logic layer.
B. . Create a mock data access layer.
. Write tests against the mock data access layer.
C. . Create a mock business logic layer and a test database.
. Configure the data access layer to target the test database.
. Write tests against the business logic layer.
D. . Create a test database from a backup of the live database.
. Configure the data access layer to target the test database.
. Write tests against the data access layer.
Answer: A
Q24. DRAG DROP
Your IT department uses a custom SharePoint list to capture help desk calls and ticket information. Management asks you to report the mean time to repair (MTTR) on a weekly basis.
You need to modify the list to capture the data necessary to prepare the report.
What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Answer:
Q25. Your development team uses Scrum as its process framework.
You need to identify key metrics for measuring the effectiveness of any process changes.
Which three key metrics should you measure? (Each correct answer presents a complete solution. Choose three.)
A. Number of story points delivered during the sprint
B. Number of tasks added to the sprint after the sprint starts
C. Number of bugs reported by testers
D. Number of classes in the code-base
E. Number of items added to the Product Backlog
F. Number of manual test cases created
Answer: ABC
Q26. You are a technical team lead. Your company network includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server.
You are assigned to work on a project with an internal development team and an off-site vendor who is new to working with your company.
You need to ensure that the code delivered by the off-site vendor is of an acceptable quality, conforms to standards, and does not affect production support.
Which three actions should you perform? (Each correct answer presents a complete solution. Choose three.)
A. Implement custom and standard check-in policies to force compliance to standards, passing of unit tests, and running static code analysis.
B. Implement a branching and permissions strategy that isolates vendor changes.
C. Implement an email alert that is triggered when the off-site vendor’s developers check in code.
D. Implement a gated check-in build.
E. Implement a policy requiring developers to shelve their changes at the end of each day.
Answer: ABD
Q27. You are developing a new application. The application will require rapid changes after it is in production.
You need to implement practices that promote high quality and ensure the code is maintainable.
Which three practices should you implement? (Each correct answer presents part of the solution. Choose three.)
A. Refactor code based on code metrics from the maintainability index.
B. Keep the code tightly coupled.
C. Create as few classes as possible.
D. Create unit tests and monitor code coverage.
E. Create as few assemblies as possible.
F. Refactor code based on code clone analysis.
Answer: ADF
Q28. Your company network includes Microsoft Visual Studio Team Foundation Server (TFS) 2012 and Microsoft System Center 2012.
You need to monitor your company’s application infrastructure.
What should you configure?
A. Event Log data collector
B. Configuration Manager
C. Application Controller
D. IntelliSense collector
E. Operations Manager
Answer: E
Explanation: Operations Manager is a component of Microsoft System Center 2012 that helps the organization monitor services, devices, and operations for multiple computers from a single console. This guide leads the reader through the process of planning the Operations Manager infrastructure by addressing the following fundamental decisions and tasks:
.ullet Identifying which services, applications, and infrastructure need to be monitored.
.ullet Determining the resources needed to employ Operations Manager to monitor the selected resources.
.ullet Designing the components, layout, security, and connectivity of the Operations Manager infrastructure.
See "Microsoft System Center 2012 - Operations Manager Guide"
http://technet.microsoft.com/en-us/library/cc507089.aspx
Configuration Manager provides key management capabilities around application delivery, desktop virtualization, device management, and security that make it possible to enable productivity amidst device proliferation – while also reducing costs.
Application Controller provides a unified console that helps you manage public clouds and private clouds, as well as cloud-based virtual machines and services.
There is no such thing as IntelliSense collector.
Q29. You are part of a scrum team that needs to identify user stories to complete in the next sprint.
What should the scrum master do?
A. Have the product owner decide which user stories to complete within the sprint.
B. Order the user stories by their story points. Select the top stories based on the team's velocity.
C. Have the team decide which user stories to complete within the sprint.
D. The scrum master should decide which user stories to complete within the sprint.
Answer: C
Q30. You manage a project for which the team has not delivered all of the story points committed to in a previous sprint.
You want to define the amount of work the team can commit to for the next sprint of the project.
What should you do?
A. Review the sprint burndown to define the amount of work.
B. Review the team velocity to define the amount of work
C. Allow the product owner to define the amount of work.
D. Review capacity of the team to define the amount of work.
Answer: B