Q111. - (Topic 1)
Your development environment includes a team project on TFSPreview. The Team Build definitions include the standard options for staging build output when using the default template.
You need to ensure that the build output is available to anyone with access to the team project. What should you do?
A. Configure a valid UNC path (in the form \\server\share).
B. Configure the source control folder named $/<Team project name>/Drops.
C. Configure the folder for any valid source control folder.
D. Configure the build output for any SharePoint document library.
Answer: B
Q112. - (Topic 1)
You are the administrator and lead developer of Microsoft Visual Studio Team Foundation Server (TFS) for Contoso, Ltd.
You identify a security issue in one of the company's projects that you support. You trace the issue to $/Contoso/src/ReadInput.cs, but that file is locked in workspace Projectl[;nicholaspiazza] by a user who is unavailable.
You need to unlock the file.
Which command should you execute?
A. tf undo $/Contoso/src/ReadInput.cs
B. tf undo [/workspace: workspacename[;nicholaspiazza]] S/Contoso/src/
C. tf lock /loclcnone S/Contoso/src/Readlnput.cs
D. tf lock /lock: checkout $/Contoso/src/ReadInput.cs
Answer: C
Explanation: http://msdn.microsoft.com/en-us/library/47b0c7w9(v=vs.100).aspx
Q113. - (Topic 1)
Your network environment is configured according to the following table:
You install Microsoft SharePoint Enterprise 2010 on a new server.
You need to change the default site collection setting for your TFS installation.
What should you do?
A. From the TFS Administration Console, update the team project collection’s SharePoint default site location.
B. From IIS Manager, create an alternate access mapping for the new SharePoint default location.
C. From the TFS Administration Console, edit the SharePoint Web Application URL.
D. From the TFS Command Prompt, run the STSADM.exe command to change the TFS SharePoint default location.
Answer: A
Q114. - (Topic 3)
Your client is utilizing the Microsoft Visual Studio Scrum 2.0 process template.
Your client provides a set of acceptance tests for Product Backlog Items (PBI). The PBI work has been committed to in the upcoming sprint.
You need to ensure that the status of the acceptance tests can be reported from TFS.
What should you do?
A. Store the acceptance test as rows in a Microsoft Excel spreadsheet and attach the spreadsheet to the PBI work item.
B. Store the acceptance test as rows in a Microsoft Excel spreadsheet. Save the spreadsheet in the associated project portal site and link it to the PBI work items.
C. Create Test case work items. Link the test cases to the PBI work items by using a Tests link type.
D. Create Test case work items. Link the PBJ work items by using a Parent link type to the test cases.
Answer: C
Q115. DRAG DROP - (Topic 1)
You are the administrator of a Microsoft Visual Studio Team Foundation Server (TFS) installation.
You are configuring a version control proxy server at a remote site.
You need to configure the proxy to cache all collections on MAINCODE and only the CommonLib collection on AUXCODE. You open the proxy's Proxy.config file.
Which code segments should you include? To answer, drag the appropriate code segments to the correct cache location. Each code segment may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
Answer:
Q116. - (Topic 2)
You are using Microsoft Test Manager (MTM). You are using the Microsoft Visual Studio Scrum 1.0 process template.
You are developing a test from an engineering document that has detailed verification information.
You need to ensure that the document is directly accessible whenever a tester runs a specific step.
What are two possible ways to accomplish this goal? (Each correct answer presents a complete solution. Choose two.)
A. Add a test step attachment.
B. Add a test case attachment.
C. Add a tested backlog items link.
D. Add a test case link.
Answer: A,B
Q117. - (Topic 2)
You are using Microsoft Test Manager (MTM).
You plan to organize the Priority 1 test cases into a test suite.
You need to create a test suite only for Priority 1 test cases.
Which type of test suite should you create?
A. query-based
B. priority-based
C. exploratory
D. requirements-based
Answer: A
Q118. - (Topic 3)
You are part of a scrum team that is trying to identify user stories to complete in the next sprint.
You and the team need to select user stories for the next sprint.
What should you do?
A. Have the product owner decide which user stories to complete within the sprint.
B. Have the scrum master decide which user stories to complete within the sprint.
C. Have the team decide which user stories to complete within the sprint.
D. Order the user stories by their story points. Select the top stories based on the team’s velocity.
Answer: C
Explanation: The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of “Done.”
Professional Scrum Development with Microsoft Visual Studio 2012 p.169
Q119. - (Topic 2)
You are using Microsoft Test Manager (MTM) to create a test plan for testing an ASP.NET website.
Your test plan needs to validate a set of critical business functionalities for the current sprint. All business functionalities are documented in the requirements document published to the project portal.
You need to associate your test plan with the requirements document.
What should you do?
A. Add a link to the requirements document in the Links section of the Properties view of the test plan.
B. Click Copy Link in the Properties view of the test plan to link the requirements document on the project portal to the test plan.
C. In the Area path drop-down list in the Properties view of the test plan, right-click the test plan area path node relevant to the requirements being tested. Select Add link to associate the requirements document link on the project portal with the area path node.
D. Click Link next to the Description box in the Properties view of the test plan to link the requirements document on the project portal to the test plan.
E. Click Link next to the Name box in the Properties view of the test plan to link the
requirements document on the project portal to the test plan.
Answer: A
Topic 3, Volume C
Q120. DRAG DROP - (Topic 3)
You have a list of tasks entered into Microsoft Visual Studio Team Foundation Server (TFS) 2012. Each task has an estimated effort and assigned to a team member.
You have limited resources available. Due to external requirements, the start date and end date of the current iteration are fixed. Several of the tasks have dependencies on one another.
You need to identify a critical path.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Answer: