Ucertify offers free demo for 70-499 exam. "Recertification for MCSD: Application Lifecycle Management", also known as 70-499 exam, is a Microsoft Certification. This set of posts, Passing the Microsoft 70-499 exam, will help you answer those questions. The 70-499 Questions & Answers covers all the knowledge points of the real exam. 100% real Microsoft 70-499 exams and revised by experts!

Q91. - (Topic 3) 

You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint. 

You need to conduct a retrospective meeting prior to planning the next sprint. 

What should you do? 

A. Analyze and revise the story points of the work items completed in the previous sprint. 

B. Analyze the previous sprint to identify what the team is going to do differently during the next sprint. 

C. Analyze items in the product backlog for the next sprint. 

D. Determine which items have been finished on the previous sprint. 

Answer:

273. - (Topic 3) 

You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process template. 

You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to complete the sprint. 

You need to ensure that the agreed upon work is assigned to team members. 

Who should be responsible for assigning work to team members? 

A. Team members 

B. Product owner 

C. Scrum master 

D. Team lead 

Answer:

Explanation: In Scrum, work should never be directed or assigned. When creating or updating a task, don’t assign it to anyone who doesn’t request the work. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.183 


Q92. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server and a virtual test infrastructure that uses Lab Manager 2012 and System Center Virtual Machine Manager (SCVMM) 2010. 

A new Hyper-V based virtual test environment is added to your network environment with its own SCVMM server. 

You need to reconfigure TFS to use the new SCVMM instance. 

What should you do? 

A. Run the TFS[.abContig.exe command. 

B. Use the TFS Administration Console. 

C. Use the Visual Studio Test Controller Configuration Tool. 

D. Use Microsoft Test Manager (MTM) in Lab Center mode. 

Answer:


Q93. DRAG DROP - (Topic 2) 

Your team uses Microsoft Test Manager to manage test cases. You are testing an ASP.NET MVC web application hosted on one of your internal servers, which is named WebSrv1. Your application connects to a SQL Server database hosted on a server named DBSrv1. 

You want to configure your test plan so that it collects diagnostic data from your test machine and all servers used by your application. 

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. 

Answer: 


Q94. - (Topic 3) 

Your company’s help desk support team comprises a single individual using an Excel spreadsheet to track tickets. 

You want to improve the flow of information between the help desk and your development team. 

You need to ensure that the lead developer receives updates only when new software defects are reported by the help desk. 

What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.) 

A. 

Create a custom list on SharePoint to capture ticket information. 

Have the lead developer subscribe to an alert for each ticket that is created with a type of 

 “software defect”. 

B. 

Use the System Center 2012 Ticket Manager to capture tickets from the help desk. 

Enable the ticket integration adapter to push tickets captured in System Center to TFS as bug work items. 

Have the lead developer subscribe to alerts for his or her assigned work items. 

C. 

Create a team project on your Team Foundation Server with a custom process template to track tickets. 

For software defects, have the help desk assign the tickets to the lead developer. 

Have the lead developer review his or her assigned tickets. 

D. 

Publish the Excel spreadsheet to a SharePoint document library. 

Configure an alert to notify the development lead when the spreadsheet is modified. 

Answer: A,C 


Q95. DRAG DROP - (Topic 2) 

Your team uses Microsoft Test Manager (MTM) to manage test cases. 

You are creating manual test cases so that your team can run the tests as part of the test process. 

You need to ensure that testers have to specify whether a test step passes or fails before they finish running the test case. 

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. 

Answer: 


Q96. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server 

(TFS) 2012 server that uses SharePoint and SQL Server 2012 Reporting Services (SSRS). 

You develop a custom report to track progress for all new projects. 

You need to ensure that the report is included in all new projects when they are created. 

Which two actions should you perform? (Each correct answer presents part of the solution. 

Choose two.) 

A. Add the report file to the TfsReports folder on the reporting server. 

B. Add a report entry to the ReportsTasks.xml in the process template. 

C. Add the report file to the Reports folder for the process template. 

D. Add a report entry to the ProcessTemplate.xml in the process template. 

Answer: A,D 


Q97. DRAG DROP - (Topic 3) 

Your IT department uses a custom SharePoint list to capture help desk calls and ticket information. Management asks you to report the mean time to repair (MTTR) on a weekly basis. 

You need to modify the list to capture the data necessary to prepare the report. 

What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.) 

Answer: 

216. - (Topic 3) 

Your team uses Microsoft Visual Studio Team Foundation Server (TFS) as their application lifecycle management solution. 

The team is developing a mission-critical internal web application. The data service and user interface are on different servers. The web application includes a Windows client The internal IT group uses packaged software to distribute software to internal clients. File shares are used for staging. The file shares are titled \\deploy\staging\myapp. and they contain the install packages. 

The team needs to deploy updates on a quarterly basis. The team also needs to keep copies of the deployed software in the team's environment and to use TFS Release Management. 

You need to create a process that deploys the Windows client to the staging area. 

What should you do? 

A. Create a custom action to deploy your msi file, and use one-click deployment. 

B. Create a Release Template, and add the step Copy file or Folder in the Staging tab. Set the Destination to \\deploy\staging\myapp. 

C. Create a Release Template, and add the Windows OS task of moving a file. Set the staging area as the place to move the msi file. 

D. Create a custom action that connects to the internal third-party deployment api, and add it to the Release Template. 

Answer:


Q98. - (Topic 3) 

You manage a highly complex project by using Microsoft Visual Studio Team Foundation Server (TFS) 2012 for application lifecycle management (ALM). 

The project has the following characteristics: 

. The development team is multi-disciplined, executes all work that is required, and has a high degree of autonomy. . A key stakeholder acts as product owner to create, prioritize, and manage dynamic 

product requirements. 

. You plan and complete requirements in three week cycles. 

. You do not need to keep track of an audit trail. 

You need to select a development process. 

What are two possible development processes you could select to achieve this goal? (Each correct answer presents a complete solution. Choose two.) 

A. MSF for CMMI Process Improvement 6.0 

B. Microsoft Waterfall 6.0 

C. Microsoft Visual Studio Scrum 2.0 

D. Microsoft Security Development Lifecycle (SDL) Process Template 

E. Microsoft Kanban 1.0 

Answer: C,E 

Explanation: You can choose based on the following considerations: 

Choose Visual Studio Scrum 2.0 or later version if your team uses Scrum, manages bugs 

along with product backlog items during sprint planning, and wants work items and 

processes designed to support Scrum. 

Choose MSF for Agile Software Development 6.0 or later version if your team uses Agile 

methods, and you resolve work items before closing them. 

Choose MSF for CMMI Process Improvement 6.0 or later version if your team requires a 

rigorous audit trail, and follows a formal process for change management. 

http://msdn.microsoft.com/en-us/library/vstudio/ms400752.aspx 

The SDL has been shown to reduce the number of vulnerabilities in shipping software by more than 50 percent. However, from an Agile viewpoint, the SDL is heavyweight because it was designed primarily to help secure very large products, such as Windows and Microsoft Office, both of which have long development cycles. 

http://msdn.microsoft.com/en-us/library/windows/desktop/ee790621.aspx 


Q99. DRAG DROP - (Topic 2) 

You are using Microsoft Test Manager (MTM) to manage your testing efforts. 

You need to produce a list of manual test runs over the past week. 

What should you do? (To answer, move the three appropriate actions from the list of 

actions to the answer area and arrange them in the correct order.) 

Answer: 


Q100. DRAG DROP - (Topic 2) 

Your team uses the Microsoft Visual Studio Scrum process template for a project. Your team uses the Area to filter by Function, with subcategories pertinent to those functions. 

Your stakeholders want to be able to view requirements and quality reports by specific department. 

You need to modify the Test Case Readiness report to add a filter so that the report can be filtered appropriately. 

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. 

Answer: