we provide Precise Microsoft 70-499 exam price which are the best for clearing 70-499 test, and to get certified by Microsoft Recertification for MCSD: Application Lifecycle Management. The 70-499 Questions & Answers covers all the knowledge points of the real 70-499 exam. Crack your Microsoft 70-499 Exam with latest dumps, guaranteed!

Q51. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server. 

Version control is configured with one project collection and two team projects. Some users use 2010 and 2012 clients, such as Visual Studio and Team Explorer Everywhere. 

You need to ensure that users will be prompted by, and can satisfy, the comments check-in policy when using both 2010 and 2012 clients. 

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.) 

A. Add the Changeset Comments policy in the team project collection’s source control settings. 

B. Add the Changeset Comments policy in the source control settings for each team project. 

C. Install the TFS 2010 Power Tools on all clients. 

D. Install the TFS 2012 Power Tools on all clients and configure the policy by using Team Explorer. 

E. Install the TFS 2010 and 2012 Power Tools on the TFS application tier and configure the policy by using Team Foundation Administrator. 

Answer: B,C 


Q52. - (Topic 2) 

You are using Microsoft Test Manager (MTM) for manual test runs. 

You are creating an action recording but some of the recorded actions were not part of the intended steps. 

You need to remove only the unwanted actions from the current action recording. 

What should you do? 

A. Open the test results and save the action log. Edit the action log to remove the unwanted actions. Import the file as an attachment, overwriting the initial action log. 

B. Reset the test case inside the test runner and create a new action log. 

C. Delete the unwanted actions from the captured actions inside the test runner. 

D. Open the test results and edit the action log to remove the unwanted actions. 

Answer:


Q53. - (Topic 1) 

Your company has a deployment of Microsoft Visual Studio Team Foundation Server (TFS), as well as a proxy server at a development site in a different country. 

You need to ensure that the proxy server can communicate with the TFS at headquarters via your company WAN. 

Which network port should you use? 

A. 80 

B. 443 

C. 8080 

D. 8081 

Answer:

Explanation: http://msdn.microsoft.com/en-us/library/ms181475.aspx 


Q54. - (Topic 2) 

You are a test developer using Microsoft Test Manager (MTM). 

You have copied a test case that has five parameters. 

You need to change the parameter names in the new test case and keep the parameter 

values intact. 

What should you do? 

A. For each parameter, click Rename parameter in the Parameter Values pane. 

B. Replace the existing parameters with new, renamed parameters. 

C. Edit each test step and rename the parameters. 

D. Copy and paste the data values from the old parameters into new parameters. 

Answer:


Q55. DRAG DROP - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. 

A developer has left the company and still has files checked out. The developer’s computer is no longer available to undo the checkouts. 

You need to undo any checked-out files for the user. You also need to delete the user’s workspace. 

What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.) 

Answer: 


Q56. - (Topic 1) 

Your software development team works within a single team project in a team project collection. You have one build controller and one build agent associated to your team project collection. 

Multiple build definitions are configured. You notice that builds occasionally wait in the queue for a long time before the build starts. 

You need to reduce the amount of time that your builds wait in the queue. 

What should you do? 

A. Change the Name filter argument on your build definition so that the build agent is found more quickly. 

B. Configure your build agent to run multiple builds at the same time. 

C. Configure additional build controllers, and associate them to the build agent already in use. 

D. Configure additional build agents, and associate them to the build controller already in use. 

Answer:

Explanation: http://social.msdn.microsoft.com/Forums/vstudio/en-US/b6d12dfa-5481-41d5-8012-1f19277b358c/tfs-2012-build-taking-a-lot-of-time?forum=tfsbuild 


Q57. - (Topic 1) 

Your client’s network environment includes a Microsoft Visual Studio Team Foundation 

Server (TFS) 2012 server. 

Some users, who do not have client access licenses perform, user acceptance testing. 

You need to allow user acceptance testers to only record and view bugs they have raised. 

What should you do? 

A. Obtain a client access license for these users. 

B. Add the users to the Contributors group. 

C. Add the users to the Work Item Only View Users group. 

D. Set user security to allow Contribute permission to a specific work item query. 

Answer:


Q58. - (Topic 3) 

Your team is setting up a test lab for the test team. Hyper-V is not the company virtualization standard. You are in a planning meeting representing the development team. 

The information technology (IT) group indicates that they are reluctant to purchase a Hyper-V server and have limited resources available for maintaining test environments. 

You need to suggest a solution for managing pre-production environments. 

What should you do? 

A. Explain that Standard Environments in Lab Management can be used, but that IT will still have to provision test VMs. 

B. Explain that TFS Lab Management is a solution, but requires Hyper-V. 

C. Explain that Standard Environments in Lab Management is a solution, but requires physical machines. 

D. Explain that Lab Management is a solution and that IT will not need to be involved since Lab Management can be used to self provision test VMs. 

Answer:

Explanation: Standard Environments: Standard environments can contain a mix of virtual and physical machines. You can also add virtual machines to a standard environment that are managed by third-party virtualization frameworks. In addition, standard environments do not require additional server resources such as an SCVMM server. SCVMM environments: SCVMM environments can only contain virtual machines that are managed by SCVMM (System Center Virtual Machine Manager), so the virtual machines in SCVMM environments can only run on the Hyper-V virtualization framework. However, SCVMM environments provide the following automation and management features that are not available in standard environments. 

http://msdn.microsoft.com/en-us/library/vstudio/dd997438.aspx 


Q59. - (Topic 2) 

You are using Microsoft Test Manager (MTM). Your development team is using Team Foundation Server (TFS) 2012 to associate requirements with source code and to automate builds. 

Your team has been testing against an old build. You want to assign a more recent automated build to the test plan. 

You need to review the requirements that have been affected between the current build and the new build before assigning it to your test plan. 

What should you do? 

A. In the Properties View of the Plan activity, click Modify the Build In Use. Select the appropriate build in the Available builds. Review the Associated work items between selected builds list. 

B. Set up a check-in policy that will force an association of a work item to the changeset. 

C. In the Assign Build view of the Track tab, click Modify. In Filter for builds, select the appropriate build to preview the list of work items. 

D. In the Queries view of the Track activity, create a custom query that lists all requirements that have the Fixed in Build field set to the new build. Run the build and review the results. 

Answer:


Q60. - (Topic 3) 

You are using the Microsoft Visual Studio Scrum 2.0 process template. You are a scrum master leading a scrum team. 

Your team is new to Agile and Lean practices. 

You need to ensure that your team communicates efficiently. 

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.) 

A. Utilize visual controls, such as task boards. 

B. Co-locate team members. 

C. Document the design of functionality you plan to build. 

D. Hold a weekly conference call with the entire team to review the bug list. 

E. Discuss issues through an email thread. 

F. Conduct daily face-to-face stand-up meetings. 

Answer: A,B,F