It is impossible to pass Microsoft 70-499 exam without any help in the short term. Come to Actualtests soon and find the most advanced, correct and guaranteed Microsoft 70-499 practice questions. You will get a surprising result by our Regenerate Recertification for MCSD: Application Lifecycle Management practice guides.
Q61. - (Topic 1)
Your client’s network environment includes a Microsoft Visual Studio Team Foundation
Server (TFS) 2012 server.
Some users, who do not have client access licenses perform, user acceptance testing.
You need to allow user acceptance testers to only record and view bugs they have raised.
What should you do?
A. Obtain a client access license for these users.
B. Add the users to the Contributors group.
C. Add the users to the Work Item Only View Users group.
D. Set user security to allow Contribute permission to a specific work item query.
Answer: C
Q62. - (Topic 3)
You are planning to develop a new application.
You need to ensure that the code is easy to test and obtain high code coverage.
What should you do?
A. Create as many static methods as possible.
B. Create a fake for each class that you are testing.
C. Ensure that concrete classes depend only on other concrete classes.
D. Ensure that each class has only one responsibility.
Answer: D
Q63. DRAG DROP - (Topic 1)
Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server.
A developer has left the company and still has files checked out. The developer’s computer is no longer available to undo the checkouts.
You need to undo any checked-out files for the user. You also need to delete the user’s workspace.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Answer:
Q64. DRAG DROP - (Topic 2)
Your company's test team is working through their bug backlog and tracking their progress on the Bugs dashboard.
The bug backlog continues to grow, but the reports that appear on the Bugs dashboard are neither accurate nor useful.
You need to establish a best practice that will ensure the reports on the Bugs dashboard are accurate and useful.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. More than one order of answer choices may be correct. You will receive credit for any of the correct orders you select.
Answer:
Q65. - (Topic 1)
Your network environment includes the following:
. Multi-tier Microsoft Visual Studio Team Foundation Server (TFS) 2012 server environment with HTTPS/ SSL configuration . Microsoft Exchange Server 2010 with SMTP listening on Port 587, requiring SSL and allowing open relay
You want to be able to inform team members about changes to projects, work items, and builds.
You need to configure email notifications for TFS 2012 using the least amount of administrative effort.
What you should do?
A.
.
Log on to the application-tier server.
.
From the TFS Administration Console, enable Email Alert Settings by entering the 5MW Server and the From address, and then editing the Advanced SMTP Settings.
B.
.
Install and configure SMTP Service by using IIS Manager on the TFS Server.
.
Log on to the application-tier server.
.
From the SharePoint Central Administration website, configure outgoing email settings.
C.
.
From the Command prompt, run the command TFSConfiq ConfigureMail /FrornEmailAddress: tfsadmin?contoso.com / SmtpHost: SMTPSVR1 /Port: 58] /SSL.
D.
.
Install and configure SMTP Service by using IIS Manager on the TFS Server.
.
Configure the TFS Email Alert Setting to use SMTP Service.
.
Configure the SMTP Service to send mail to Exchange by using port 587 and SSL.
Answer: A
Q66. - (Topic 1)
Your company's Microsoft Visual Studio Team Foundation Server (TFS) installation has a
robust data tier that includes a Data Warehouse Server and Microsoft SQL Server Analysis Services.
During the typical processing of your data warehouse, you see that the length of time it takes for the warehouse adapters to pull data from the operational store, transform it, and then write it to the warehouse is incrementally increasing.
You need to decrease the time between refreshes in order to reduce the processing time.
Which service should you access to change the settings?
A. AdministrationService
B. JobsService
C. TeamProjectCollectionService
D. WarehouseControlWebService
Answer: D
Explanation: http://msdn.microsoft.com/en-us/library/ms244694.aspx
Q67. - (Topic 3)
You manage a development team that has been assigned the task of developing a reporting application. The team holds a kickoff meeting with the stakeholders to document user requirements.
You review the draft requirements list that results from this meeting.
You need to indicate which requirements likely will require rework before you can send the requirements list to the development team.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Identify requirements that are independent of other requirements. These requirements likely will need to be integrated with the other requirements.
B. Identify requirements that cannot be tested easily. These requirements likely will need details to make them more testable.
C. Identify requirements that do not have estimates. These requirements likely will need additional details before they can be approved.
D. Identify requirements that depend on other requirements. These requirements likely will need to be split.
E. Identify requirements that provide little business value. These requirements likely will need to be reconsidered.
Answer: C,D,E
Q68. - (Topic 2)
You are a QA tester on a development team. You are responsible for a large number of test cases on your current project.
You need to bulk edit test steps in a large group of test cases.
Which tool should you use?
A. Web Test case Management
B. Microsoft Excel
C. Microsoft Visual Studio
D. Microsoft Test Manager
Answer: A
Explanation: What's new in testing the application in Visual Studio 2013
Q69. - (Topic 2)
You are using Microsoft Test Manager (MTM). You are using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement process template. Your Team Foundation Server (TFS) 2012 server is configured to support reporting.
You are tracking testing progress for the requirements in the iteration.
You need to identify the report that provides the following:
Verify that all requirements are covered by test cases.
Determine the number of hours of work remaining for each requirement.
Determine the percentage of completion for each requirement.
Determine the number of bugs for each requirement.
Which report should you use?
A. Requirements Overview
B. Test Case Readiness
C. Remaining Work
D. Test Plan Progress
Answer: A
....
Q70. - (Topic 1)
Your client’s network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server installed at its main office.
The network administrator at a remote office reports high WAN utilization. Users at the remote office report slow response times when downloading source code.
You need to minimize WAN utilization and improve the response times for downloading source code.
What should you do?
A. Install TFS Server at the remote site and set up database synchronization between the existing TFS Server and the remote site.
B. Install and configure TFS Proxy at the remote site. Point the TFS Proxy to the TFS server and point Team Explorer to the TFS Proxy.
C. Install and configure IIS caching. Point Team Explorer to the IIS server.
D. Install TFS Proxy at the remote site. Configure TFS Proxy to point to the TFS Server and configure each user’s Visual Studio Source Control to use the proxy server for file downloads.
Answer: D