Want to know Pass4sure 74-343 Exam practice test features? Want to lear more about Microsoft Managing Projects with Microsoft Project 2013 certification experience? Study Verified Microsoft 74-343 answers to Improve 74-343 questions at Pass4sure. Gat a success with an absolute guarantee to pass Microsoft 74-343 (Managing Projects with Microsoft Project 2013) test on your first attempt.

2021 Nov project 74-343:

Q1. RAG DROP 

You are an independent project manager who uses Project Professional 2013 and wants to extend the standard functionalities of it. 

You need to find and install an app from the Office Store. 

Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.) 

Answer: 


Q2. You are a resource manager who uses Project Standard 2013. 

You manage all of your resources in a single plan, which acts as a Shared Resource Pool 

for other projects in your organization. Each resource needs to pass an annual exam in 

order to work on construction sites. 

You need to set up a method that allows you to pick the renewal month for each resource. 

What should you do? 

A. Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month when the exam expires. Select the correct expiration date for each resource. 

B. Use the Organizer to copy the Resource Finish1 Custom field from the Global.mpt. Select the correct expiration date for each resource. 

C. Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup table with values containing the last date of each month. Select the correct expiration date for each exam. 

D. Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup table with monthly values. Select the correct expiration month for each exam. 

E. Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration dates into a Lookup table. Select the correct expiration date for each resource. 

Answer:


Q3. Your organization uses Microsoft Project 2013. 

You are finalizing the Project Schedule for a very complex project with over 100 resources. 

You need to ensure that all tasks are assigned to resources. 

What should you do? 

A. Use Task Usage view and look for Unassigned tasks. 

B. Use Resource Graph view and look for the Unassigned resource name. 

C. Use Resource Usage view and look for the Unassigned resource name. 

D. Use Resource Sheet view and look for Unassigned tasks. 

Answer:


Q4. You are a project manager who uses Project Standard 2013. 

You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in size. 

You need to share this project plan by email with your team and ensure that they can easily access the documents. 

What should you do? 

A. In the Task Information notes, insert an object from a file. Uncheck the Link option and make sure that it is a document, not a link. Select your document and click on it. Project will automatically create the reference to this document. 

B. Create a task custom field named Link to Document, and select the field type as Text Hyperlink. Copy the SharePoint URL of each document and paste it as a text into the Link to Document task custom field. Project Standard 2013 will convert this text to a clickable hyperlink. 

C. Copy and paste the document into your Gantt chart, and create a link between your task and the document. 

D. Go to backstage and use the feature Add and Link a SharePoint Document to My Tasks to select your document in your SharePoint Library. Select your task. Project will automatically create a clickable hyperlink. 

E. Copy the SharePoint URL of each document and paste in the Hyperlink task standard field as a text. Project will convert this text to a clickable hyperlink. 

Answer:


Q5. You are a project manager for a company that uses Project Professional 2013. 

You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table. 

You need to communicate the progress of tasks that have a finish date of either October 2 or October 22. 

What should you do? 

A. Go to the Task tab, open the Find window, and set the parameters to find the required dates, setting the Look in Field to Finish. Then click Find Next. 

B. Go to the View tab, open the More Views window, and create a new view. 

C. Go to the View tab and use the Date Range filter. 

D. Go to the View tab and select Display AutoFilter. Click on the arrow next to the Finish column and check only the required dates. 

Answer:


Latest microsoft 74-343 certification exam:

Q6. You are using Project Standard 2013. 

You want the ability to see only tasks that have finish dates past their deadline date 

You need to achieve this goal using a custom field. 

What should you do? 

A. Create a Lookup containing the values Yes and No against the Task Text1 custom field. Write a formula that compares the deadline date to the finish date and displays the correct value from the Lookup table. 

B. Use the Task Flagl5 custom field. Write a formula that compares the deadline date to the finish date, and set the result to Yes or No. 

C. Use the Task Text30 custom field, also known as the Deadline Flag, since it automatically provides this capability. 

D. Rename the Task Number1 custom field to Deadline passed. Write a formula that compares the deadline date to the finish date and displays Yes or No in the field. 

Answer:


Q7. RAG DROP 

You are a project manager who uses Microsoft Project 2013. 

A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time. 

You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed. 

Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.) 

Answer: 


Q8. Your company uses Project Professional 2013. 

You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task. 

You need to set up a dependency between these two tasks. 

What should you do? 

A. Create a Start to Start predecessor relationship from the Create Solution Test Plan task to the Test Solution task. Set a lead time of three days. 

B. Create a Start to Start predecessor relationship from the Test Solution task to the Create Solution Test Plan task. Set a lead time of three days. 

C. Create a Finish to Start predecessor relationship from the Test Solution task to the Create Solution Test Plan task. Set a lag time of three days. 

D. Create a Finish to Start predecessor relationship from the Create Solution Test Plan task to the Test Solution task. Set a lag time of three days. 

Answer:


Q9. RAG DROP 

You are a senior project manager in a software development company. You manage your projects with Project Professional 2013. 

The development team is behind schedule due to a problem found in the architectural design of the database. The lead architect estimates that redesigning the database will take approximately 30 hours. You create a new manual task and assign it to the lead architect. However, the task has not been scheduled. 

You need to easily see a time phased view of all tasks for the lead architect in order to schedule the task for completion. 

Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.) 

Answer: 

69. You work as a project manager for a construction company that uses Project Professional 2013. 

You have created your work breakdown structure (WBS) and are adding resources to your tasks. However, one of your tasks requires multiple resources. You have the name of the project's lead support individual, and you have been provided with the equivalent of three full-time support resources. These three resources are not named individuals but are part of a group. 

The actual individuals from this group will change based on coverage schedules. 

The resources have the following cost structures: 

.

 The lead is billed out at S175/hour. 

.

 The group resources are billed out at $140/hour. 

You need to add these resources to the schedule and track your project costs. 

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.) 

A. Add the named resource to the task with an allocation of 100% and a standard rate of $175/hour. 

B. Add the named resource to the task with an allocation of 400% and a standard rate of $157.50/hour. 

C. Add the group resource to the task with an allocation of 300% and a standard rate of $140/hour. 

D. Add the group resource to the task with an allocation of 100% and a standard rate of $l40/hour. 

Answer: A,C 


Q10. You are a project manager for a company that is based in New York and London. The company uses Project Professional 2013. 

Teams from both offices are working together on a project. Since the two offices are located in different regions, the teams have separate company holiday schedules and working times. 

You need to ensure that the effort for each resource and task is set up properly in the calendar. 

You want to achieve this goal by using the least amount of time and effort. 

What should you do? 

A. Create a London calendar from the standard calendar and assign the London calendar as the project calendar. 

B. Create a new base calendar for London that includes all of the London office's company holidays and assign it to all London resources. 

C. Manually edit each London resource's calendar to add all of the London office's company holidays. 

D. Assign the 24-hour calendar to all tasks and select Scheduling ignores resource calendars. 

Answer: