getcertified4sure.com

[Renewal] mb5-705 surestep




Doing MB5-705 certification exams can be a challenge for people who are doing work full occasion or studying to get a graduate or submit graduate degree. There is a far more simple and also effective tactic for the preparation of Microsoft MB5-705 tests at Actualtests. By simply doing each of our Microsoft MB5-705 practice materials, you are going to be competent at getting a high score that maintains your passing the actual exam. Were proud of ourselves on the achievement of 100% passing ratio in MB5-705 exam. We now have a conscientious team. The particular experts exert just about all their energies in order to keep this kind of Microsoft Microsoft study supplies up to date. Today we have the actual latest and also comprehensive version of Microsoft MB5-705 exam questions and also practice tests on the internet site. You will have the ability to go through your Microsoft Microsoft exam paper smoothly if you keep tempo with the Microsoft MB5-705 study guide. Youll just invest a little money and occasion taking the actual Microsoft MB5-705 online simulation exam or even studying the MB5-705 practice supplies. It is a great utterly shortcut to Microsoft Microsoft certification.

2021 Dec mb5-705 vs mb5-858:

Q41. You are a project manager working with a client who has specific feature needs, moderate to complex customizations, and minimal business process mapping completed. 

You need to recommend a project type for the client. 

Which project type should you recommend? 

A. agile 

B. enterprise 

C. standard 

D. rapid 

Answer:

Explanation: 

Agile Implementation: Uses an iterative, incremental process for developing Microsoft Dynamics Solutions. This project gives customer greater control over the final solution because customers can quickly change the direction of the solution from one sprint cycle to next.Typically used at a single site requiring specific features and moderate to complex customizations. 

References: 

http://www.ignify.com/ERP-Implementation-Methodology.asp http://social.technet.microsoft.com/wiki/contents/articles/5768.microsoft-dynamics-sure-step-agile-implementation.aspx 


Q42. You completed a Decision Accelerator Offering and need to document the key conclusions. Which group of documents should you use? 

A. process review documents 

B. efficiency instruments 

C. customer sign-off documents 

D. validation documents 

Answer:

Explanation: Reference:http://download.microsoft.com/download/3/1/E/31EB40F6-AF51-4975-8D1C-52E323C8492A/01-DA-AX_Datasheet_Oct-2011.pdf 

http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx 

http://technet.microsoft.com/en-us/library/aa496439.aspx 


Q43. Which two components are critical to the success of user acceptance testing? (Each correct answer presents part of the solution. Choose two.) 

A. the completion of the end user training 

B. the building of the disaster recovery environment 

C. the usage of user acceptance test scripts 

D. the transactions to use for the tests 

Answer: A,C 

Explanation: A: The standard Sure Step process defines that end user training is required prior to user acceptance testing. 

C: Together with the key users, we can now prepare the user acceptance test scripts that will guide the UAT (user acceptance testing) during the Deployment phase. 

Note: 

http://technet.microsoft.com/en-us/library/aa496439.aspx 


Regenerate braindump mb5-705:

Q44. What is the Project Management Institute (PMI) definition of a project? 

A. A project is unique and contains temporary activities defined by the customer. 

B. A project is a temporary endeavor undertaken to create a unique product, service, or result. 

C. A project is unique and contains a vision, scope, and objectives defined by the customer. 

D. A project is a set of goals and objectives to satisfy a customer’s needs. 

Answer:


Q45. You are preparing for a go live cutover. 

You need to create the go live cutover document. 

Which items should you add to the document? 

A. the operational and support activities for production operations 

B. the detailed process steps to be included in the cutover 

C. the details of the production environment and disaster recovery information 

D. a high-level overview of cutover activities and those involved 

Answer:

Explanation: Chapter 8 — Planning Phase: Creating the Project Plans http://technet.microsoft.com/en-us/library/bb497050.aspx 


Q46. You are a project manager, and you use Microsoft Dynamics Sure Step Methodology to manage projects. You need to ensure that quality assurance is part of a project that you are managing. Which item should you include as part of the project? 

A. a comprehensive review with the project stakeholders at the end of the project 

B. a review process done at the beginning and checked off at the end of the project with the project stakeholders 

C. quality assurance reviews with stakeholders, scheduled early and often across all project phases 

D. a comprehensive review process performed if problems occur during the project or at a stakeholder's request 

Answer: