It is impossible to pass Microsoft MB6-700 exam without any help in the short term. Come to Exambible soon and find the most advanced, correct and guaranteed Microsoft MB6-700 practice questions. You will get a surprising result by our Abreast of the times Microsoft Dynamics AX 2012 R2 Project practice guides.
Q21. You need a quick snapshot view of a project’s progress. Which form should you use?
A. Invoice control
B. Project statements
C. Cash flow
D. Cost control
Answer: B
Q22. You need to set up a pay when paid (PWP) term for a project. Which project type should you choose?
A. time and material
B. internal
C. cost
D. fixed-price
Answer: A
Q23. To which funding type can you apply payment retention?
A. On hold
B. Grant
C. Organization
D. Customer
Answer: D
Q24. You are planning to install a Microsoft Dynamics NAV client by using Group Policy. Which two statements are correct about the Software Distribution Point (SDP)? (Each correct answer presents a complete solution. Choose two.)
A. The folder that is used as the SDP must be located on the Microsoft Dynamics NAV Server.
B. The folder that is used as the SDP may only contain .MSI files.
C. Users must have Read access on the folder that is used as the SDP.
D. Administrators must have sufficient permissions on the folder that is used as the SDP to change the package files.
Answer: CD
Q25. You configure a timesheet workflow. What is the Assignment function used to define?
A. conditions for approval of the timesheet
B. notifications after approval of a timesheet
C. submitters of the timesheet
D. reviewers of the timesheet
Answer: D
Q26. Which statement about the customer advance feature is true?
A. The customer advance cannot be created once transactions have been posted to the project.
B. The customer advance is created by using the payment journal.
C. The customer advance can be used to offset billable charges by using the invoice proposal process.
D. The customer advance amount can be defined as a percentage of an existing invoice amount.
Answer: C
Q27. For which two project types can on-account forecasting be used? (Each correct answer presents part of the solution. Choose two.)
A. cost
B. fixed-price
C. investment
D. time and material
Answer: BD
Q28. You are responsible for a customer’s fixed-price project. The customer requests that you provide additional spare parts. The purchase of these spare parts falls outside the scope of the project. You need to ensure that the customer is charged for the spare parts. How should you create the sales order so that the customer is invoiced for the spare parts?
A. Create the sales order by using a subproject of the type cost.
B. Create the sales order by using a subproject of the type time and material.
C. The sales order cannot be created because this is a fixed-price project.
D. Create the sales order from the fixed-price project and ensure that the line property for the order lines is chargeable to the customer.
Answer: B
Q29. You set up a project validation feature. You need to ensure that a particular project is available for only selected workers. Which two types of validation should you configure? (Each correct answer presents part of the solution. Choose two.)
A. worker validation project assignment
B. worker/project validation group
C. project validation worker assignment
D. worker/category validation group
Answer: BC
Q30. You are planning to deploy the Microsoft Dynamics NAV RoleTailored client. You need to assign the client application to all users. Which tool should you use?
A. the Services snap-in
B. the Local Users and Groups snap-in
C. the Microsoft Dynamics NAV snap-in
D. the Group Policy Management Editor snap-in
Answer: D