Proper study guides for Up to the minute Microsoft Microsoft Dynamics AX 2012 R2 Project certified begins with Microsoft MB6-700 preparation products which designed to deliver the High quality MB6-700 questions by making you pass the MB6-700 test at your first time. Try the free MB6-700 demo right now.
Q31. Which two tools enable you to control a project? (Each correct answer presents part of the solution. Choose two.)
A. project forecasts
B. project quotations
C. project budgets
D. project statements
Answer: AC
Q32. Which three parameters are required when entering the hours forecast for a project? (Each correct answer presents part of the solution. Choose three.)
A. category
B. cost price
C. activity
D. number of hours
E. funding source
Answer: ABD
Q33. You set up a new internal project. You need to manually create a hierarchical representation of the activities for the project. Which form should you use?
A. Activities
B. Assign resources
C. Work breakdown structure template
D. Work breakdown structure
Answer: D
Q34. Which funding source type can appear only once on a project contract?
A. On hold
B. Grant
C. Customer
D. Organization
Answer: A
Q35. What can the Resource assignment analysis report do that the Resource assignments report cannot do?
A. It can show how many hours a resource is assigned to a project.
B. It can show availability of a resource.
C. It can be filtered to include certain commitment types.
D. It can be filtered to include a specified date range.
Answer: B
Q36. Which task is allowed after a budget is approved?
A. creating an additional project budget for the project
B. creating a general ledger budget for a new subproject
C. reallocating a project budget from another project
D. building a forecast model from the project budget
Answer: C
Q37. A company is planning to install the Microsoft Dynamics NAV RoleTailored client on multiple client computers. Some client computers run a 32-bit operating system while others run a 64-bit operating system. You need to select a Group Policy setting to ensure that the client application is deployed to all client computers. Which option should you select?
A. Include OLE information when you deploy applications
B. Auto-install this application by file extension activation
C. Make 32-bit X86 Windows Installer applications available to Win64 computers
D. Maximum
Answer: C
Q38. Which item is a valid funding type for a project contract?
A. Project
B. Customer
C. Vendor
D. Ledger
Answer: B
Q39. You attach an invoice format to the project contract. Which item is controlled by the invoice format setting?
A. invoice output destination
B. invoice currency
C. invoice summarization
D. invoice orientation
Answer: C
Q40. Which item is used to transfer costs from work in process (WIP) accounts to profit and loss accounts?
A. Post costs form
B. Adjustments form
C. On-account posting
D. Expense journal
Answer: A