Apply Examcollection Microsoft MB6-884 test out inquiries to gain access to the Product Good quality. Youll not refrain from purchasing the MB6-884 Exam Problems mainly because it?¡¥s the ultimate on-line MB6-884 Examine Material. 1000s of successful online MB6-884 applicants have got passed the precise MB6-884 Exam with the MB6-884, and so are you going to!
Q1. - (Topic 1)
Which element defines the Work in Process (WIP) ledger accounts for a Lean manufacturing production flow?
A. cost group
B. costing version
C. production group
D. Value Stream
Answer: C
Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Production flows and activities, White Paper, April 2011, p 33.
Q2. - (Topic 2)
What is a valid exception to the standard cost requirement in Microsoft Dynamics AX 2012?
A. a manufacturing Kanban with Update on hand on pick and Update on hand on receipt both set to Yes
B. a manufacturing Kanban with Update on hand on pick and Update on hand on receipt both set to No.
C. a withdrawal Kanban with Update on hand on pick and Update on hand on receipt both set to No.
D. a withdrawal Kanban with Update on hand on pick and Update on hand on receipt both set to Yes.
Answer: C
Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Production flows and activities, White Paper, April 2011, p 28-30.
Q3. - (Topic 1)
You are creating event Kanban rules in Microsoft Dynamics AX 2012.
You need to replenish material that is required for a downstream process activity.
Which event type should you activate?
A. Kanban line event
B. stock replenishment event
C. sales event
D. BOM line event
Answer: A
Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Kanban and Pull Based Manufacturing, White Paper, July 2011, p 8.
Q4. - (Topic 2)
In Microsoft Dynamics AX 2012, you create a work cell that has a capacity model setting of Throughput. Which of the following values are used to calculate the capacity load of a Kanban job on the work cell? (Each correct answer presents a partial solution. Choose three.)
A. start date
B. cycle time
C. Kanban quantity
D. throughput ratio
E. unit correction factor
Answer: B,C,D
Reference: Microsoft Dynamics AX 2012, Lean Manufacturing: Kanban and Pull Based Manufacturing, White Paper, July 2011, p 10.
Q5. - (Topic 1)
From where can you manually create an event Kanban for Kanban line events? (Each correct answer presents a complete solution. Choose two.)
A. pegging tree
B. sales order line
C. Kanban board for process jobs form
D. Kanban rules form
Answer: C,D
Reference: http://msdn.microsoft.com/en-us/subscriptions/hh781101.aspx http://msdn.microsoft.com/en-us/subscriptions/hh227370.aspx
Topic 2, VolumeB
Q6. - (Topic 2)
Which cost category of a work cell is considered in costing for Lean manufacturing in Microsoft Dynamics AX 2012?
A. setup
B. quantity
C. direct outsourcing
D. run time
Answer: D
Reference:
http://technet.microsoft.com/en-us/library/hh208503.aspx
Q7. - (Topic 1)
At what level is the standard cost maintained for products that are included in a production flow?
A. item model group level
B. item group level
C. item number level
D. site level
Answer: D
Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Production flows and activities, White Paper, April 2011, p 34.
Q8. - (Topic 1)
Which of the following actions can be performed when processing with the supply schedule in Microsoft Dynamics AX 2012? (Each correct answer presents a complete solution. Choose three.)
A. create a new scheduled Kanban
B. create a new planned order
C. run Master Scheduling
D. delete planned orders
E. link a Kanban rule to a production flow
Answer: A,B,C
Reference:
http://dynamicscare.com/blog/index.php/using-the-supply-schedule-in-dynamics-ax-2012/
Q9. - (Topic 1)
What is created from a purchase agreement to signal demand for a product or service provided by a subcontractor in Microsoft Dynamics AX 2012?
A. manufacturing Kanban
B. sales order
C. event Kanban
D. release order
Answer: A
Reference:
Microsoft Dynamics AX 2012, Lean Manufacturing: Production flows and activities, White Paper, April 2011, p 44.
Q10. - (Topic 2)
Which statement is true when Include safety stock is selected in a Kanban quantity calculation policy?
A. The safety factor is excluded.
B. a Kanban simple formula is created.
C. A service level is required.
D. Demand during lead time is considered constant.
Answer: C