Download of PK0-004 study guide materials and free samples for CompTIA certification for examinee, Real Success Guaranteed with Updated PK0-004 pdf dumps vce Materials. 100% PASS CompTIA Project+ Certification Exam exam Today!
Q11. A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
A. Sponsor
B. Project manager
C. Project management office
D. Project team
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 108
Q12. Which of the following documents should be used to provide high-level reporting to key stakeholders?
A. Dashboard
B. Communication plan
C. Statement of work
D. Project charter
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 325
Q13. A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:
A. quality control issues.
B. additional risks.
C. scope creep.
D. time constraints.
Answer: D
Q14. A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
A. Project schedule
B. Balanced scorecard
C. Issue log
D. Status report
Answer: D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 328
Q15. A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
A. Backlog
B. Standup
C. Kickoff
D. Retrospective
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 306
Q16. Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?
A. Discontinue the meetings with the poorest attendance.
B. Decrease the length of the meetings.
C. Distribute an agenda before each meeting.
D. Document team member attendance and report it to management.
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 326
Q17. A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?
A. Update the project management plan.
B. Issue a change request.
C. Revise the project charter.
D. Evaluate the impact to the baseline.
Answer: D
Q18. A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management methodology for this requirement?
A. Waterfall
B. Agile
C. PRINCE2
D. Bottom-up
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 310
Q19. A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
A. Cost, schedule, organizational chart, and risks/issues
B. Risks/issues, cost, RACI chart, and action items
C. Schedule, cost, risks/issues, and milestones
D. Action items, organizational chart, schedule, and NDA
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 326
Q20. There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A. A, C, G
B. A, B, F
C. D, E, H
D. D, B, F
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 175