getcertified4sure.com

PRINCE2-Foundation Exam

How to win with prince2 foundation exam questions and answers free




Cause all that matters here is passing the PRINCE2-Exams prince2 foundation course exam. Cause all that you need is a high score of prince2 foundation exam questions and answers free PRINCE2 Foundation exam exam. The only one thing you need to do is downloading Pass4sure prince2 foundation exam questions and answers free exam study guides now. We will not let you down with our money-back guarantee.

Q1. - (Topic 2) 

Which is a purpose of a Project Product Description? 

A. Records the costs and timescales for delivery of the project's final product 

B. Shows the dependencies between the project's products to aid planning 

C. Provides a list of all the products to be delivered by the project 

D. Defines what the project must deliver in order to gain acceptance 

Answer:


Q2. - (Topic 2) 

Which is a purpose of a Lessons Log? 

A. Note any lessons that are raised in Checkpoint Reports 

B. Record that corrective action is being taken 

C. Escalate lessons to the Project Board 

D. Raise improvements with Project Assurance 

Answer:


Q3. - (Topic 1) 

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties. 

A. Stage Plan 

B. Communication Management Strategy 

C. Follow-on action recommendations 

D. Quality Management Strategy 

Answer:


Q4. - (Topic 1) 

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete? 

A. Executive 

B. Senior User 

C. Senior Supplier 

D. Project Manager 

Answer:


Q5. - (Topic 1) 

Which is an objective of the Initiating a Project process? 

A. Develop the corporate quality management system as part of the Project Initiation Documentation 

B. Prepare the plans for the subsequent stages 

C. Summarize how the organization's project management method will be tailored for the project 

D. Request authority from corporate management to deliver the project 

Answer:


Q6. - (Topic 1) 

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment? 

A. Specify the desired result 

B. Provide the resources and skills to deliver the desired result 

C. Pay for the project 

D. Specify the benefits of the project 

Answer:


Q7. - (Topic 1) 

Which of the following statements about stakeholders are true? 

1. 

Someone who thinks they will be affected by a project is a stakeholder on that project. 

2. 

Stakeholders may be internal or external to the corporate organization. 

A. Only 1 is true 

B. Only 2 is true 

C. Both 1 and 2 are true 

D. Neither 1 or 2 are true 

Answer:


Q8. - (Topic 2) 

Which is a recommended quality review team role? 

A. Project Manager 

B. Assurance 

C. Project Support 

D. Administrator 

Answer:


Q9. - (Topic 1) 

Which is a typical core activity within configuration management? 

A. Issue management 

B. Quality inspection 

C. Identification 

D. Preparation 

Answer:


Q10. - (Topic 1) 

Which is a purpose of the Directing a Project process? 

A. Create and authorize the project mandate 

B. Ensure that work on products allocated to the team is authorized and agreed 

C. Control the day-to-day running of the project 

D. Delegate day-to-day management of the project to the Project Manager 

Answer: