By creating the utmost regarding our Microsoft 70-496 products which contain 70-496 exam question as well as answers, you are bond to get through the Microsoft genuine test. All of us guarantee your success using the help regarding Microsoft 70-496 professionally written practice questions as well as answers at Exambible. The Microsoft practice materials gives you comprehensive training for the 70-496 exam syllabus. Cracking the actual Microsoft Microsoft exam is no problem with our precise, accurate as well as logical dumps. The feedback as well as high passing ratio can easily prove our promise. All of us offer a person the money-back policy in case you fail in the 1st attempt after utilizing Microsoft 70-496 products.

2021 Oct mva 70-496:

Q31. DRAG DROP 

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. 

You need to configure TFS to send an email notification to a group of testers when a build is completed. 

What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.) 


Answer: 



Q32. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server and a virtual test environment that uses Lab Management 2012 along with System Center Virtual Machine Manager (SCVMM) 2010. 

You want to install a test virtual machine that is hosted within a lab environment. 

You need to ensure that the test virtual machine can support all the features of Lab Management 2012. 

Which component should you install on the test virtual machine? 

A. Agents for Visual Studio 2012 

B. Visual Studio Build Agent 2012 

C. Visual Studio Test Agent 2012 

D. Visual Studio Lab Agent 2012 

Answer: A 


Q33. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. You have two teams named Team A and Team B working on a team project. 

You assign work items to a team area for each team. Each person belongs to only one team. 

You need to provide read-only access to work items in the Team A area node to Team B by using the least number of permissions changes. 

What should you do? 

A. Set the View Work Items in This Node permission to allow Team B to access the Team A node. 

B. Set the Edit Work Items in This Node permission for Team B as Deny for the Team A node. 

C. Set the Edit Work Items in this Node permission for Team B as Deny to the Team A node and each child of the Team A node. 

D. Set the View Work Items in This Node permission to allow Team B to access the Team A team node and each child node. 

Answer: B 


Q34. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server that has separate computers for the application tier and the data tier. 

The data-tier computer experiences hardware failure. You restore all the data of TFS on another computer in the network by using a backup. 

You need to provide the location of the restored database to the application tier of TFS without reinstalling the application tier. 

What should you do? 

A. Use the Team Foundation Backups node of the TFS Administration Console. 

B. Use the Application Tier node of the TFS Administration Console. 

C. Run the Tfsmqmt.exe configure command. 

D. Run the TfsConfig reqisterDB command. 

Answer: D 


Q35. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. 

You need to rebuild both the Team Foundation Data Warehouse and the SQL Server Analysis Services Cube from scratch. 

What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.) 

A. Use Microsoft SQL Server Management Studio. 

B. Use SQL Server Business Intelligence Development Studio. 

C. Use Warehouse Control Web Service. 

D. Use the Reporting section in Team Foundation Administration Console. 

E. Restart SQL Server Analysis Services service, SQL Server service, and SQL Server Agent service by navigating to the Services option under Administrative Tools. 

Answer: CD 


Regenerate 70-496 free dumps:

Q36. Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server. A single build machine is installed with one controller and two agents. The working directories are configured to use the following working directory: 

$(SystemDrive)\Builds\$(BuildAgentId)\$(BuildDefinitionPath). 

Your system drive is running out of space and some builds often fail with the following error: 

“The specified path, file name, or both are too long. The fully qualified file name must be less than 260 characters, and the directory name must be less than 248 characters.” 

You need to meet the following requirements: 

What should you do? 

A. Set the Build Agent working directory path to D:\BId\$(BuildAqentld)\$(BuildDetinitionPath). 

B. Create a system variable named BuildDrive and set its value to D:\. 

C. Set the Build Service working directory path to D:\BId\$(BuildAqentld)\$(BuildDefinitionPath). 

D. Set the Team Foundation Build variable named $(BuildDrive) to the value D:\. 

Answer: A 


Q37. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. Your development team uses Visual Studio 2012. 

You store specialized design files within your Visual Studio solution by using version control. These design files are stored in a proprietary binary format and use the filename extension .dzn. 

You need to meet the following requirements: 

What should you do? 

A. Within the Source Control Explorer, right-click each .dzn file and uncheck the Allow multiple check outs option. 

B. Add a new file type for .dzn to the Team Project Source Control Settings and clear the Enable file merging and multiple check out checkbox. 

C. Within the Visual Studio Options dialog box for Source Control, add the .dzn extension to the Prevent multiple check-outs for the following file types list in the Visual Studio Team Foundation server node. 

D. Add a new file type for .dzn to the Team Project Collection Source Control Settings and clear the Enable file merging and multiple check out checkbox. 

Answer: D 


Q38. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. 

You lead a team of testers that is testing a specific module of an application. You want to list only the test cases that are assigned to you testers. 

You need to create a query on work items of the type Test Case. 

What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.) 

A. . Create a team project level group for testers of your module. 

. Create a work item query that uses the = operator on the Assigned To field and the group of testers. 

B. . Create a team for testers of your module. 

. Create a work item query that uses the = operator on the Assigned To field and the team of testers. 

C. . Create a team project level group for testers of your module. 

. Create a work item query that uses the IN GROUP operator on the Assigned To field and the group of testers. 

D. . Create a team for testers of your module. 

. Create a work item query that uses the IN GROUP operator on the Assigned To field and the team of testers. 

Answer: CD 


Q39. Your network environment includes an on-premise Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. You create a work item custom query named Tasks Exceeding Original Estimate Hours in your My Queries folder. 

You need to meet the following requirements: 

What should you do? 

A. From within Team Web Access: 

. From the Activities list on the home page, click Publish Query to Team Favorites. 

. Select the Tasks Exceeding Original Estimate Hours query from the list overlay. 

B. From within Team Explorer: 

. From the Activities tab, click Publish Query to Team Favorites. 

. Select the Tasks Exceeding Original Estimate Hours query from the list overlay. 

C. From within Team Explorer: 

. From the My Queries folder, drag the Tasks Exceeding Original Estimate Hours query to the Shared Queries section. 

. Drag the query from the Shared Queries section to the Team Favorites section. 

D. From within Team Web Access: 

. On the Work Items tab of the Work page, drag the query Tasks Exceeding Original Estimate Hour that appears in the My Queries section and add it to Shared Queries section. 

. Drag the query from the Shared Queries section to the Team Favorites section. 

Answer: C 


Q40. Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. All requests pass through an HTTP proxy before reaching users. 

You need to allow access to the server over HTTPS for remote workers. 

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.) 

A. Configure Basic authentication. 

B. Configure SSL. 

C. Configure Kerberos authentication. 

D. Add the users to the user identities in Internet Information Services (IIS). 

E. Configure a TFS proxy server. 

Answer: AB