Master the HPE0-S58 Implementing HPE Composable Infrastructure Solutions content and be ready for exam day success quickly with this Actualtests HPE0-S58 exam answers. We guarantee it!We make it a reality and give you real HPE0-S58 questions in our HP HPE0-S58 braindumps.Latest 100% VALID HP HPE0-S58 Exam Questions Dumps at below page. You can use our HP HPE0-S58 braindumps and pass your exam.

Online HP HPE0-S58 free dumps demo Below:

NEW QUESTION 1
Refer to the exhibit.
HPE0-S58 dumps exhibit
A Synergy integrator needs to establish the module cluster links between two master modules, as shown. Which ports can the integrator use for the module cluster links?

  • A. 1 and 2
  • B. 3 and 4
  • C. 5 and 6
  • D. 7 and 8

Answer: D

Explanation:
References:
https://support.hpe.com/hpsc/doc/public/display?docId=emr_na-a00017673en_us&docLocale=en_US (15)

NEW QUESTION 2
Which policy can an integrator apply when creating a datastore using HPE OneView for vCenter Server?

  • A. Data at Rest encryption policy
  • B. Round Robin load balancing policy
  • C. Recovery Manager Central policy
  • D. virtual machine Restart policy

Answer: C

NEW QUESTION 3
A customer is planning to deploy OneView for vCenter Server to improve management procedures for growing virtualization environment. The customer is concerned about resources required by HPE OneView for vCenter Server.
Which statement about deploying HPE OneView for vCenter Server is true?

  • A. It is deployed as an application on the Windows Server machine with at least 48GB of memory.
  • B. It is deployed as a part of the HPE Composer installation.
  • C. It is deployed as a virtual machine on the supported hypervisor.
  • D. It can only be deployed if HPE Global Dashboard is already installed.

Answer: C

NEW QUESTION 4
Which component must be deployed at the customer site and is essential for HPE InfoSight for Servers?

  • A. HPE Intelligent Provisioning
  • B. HPE Global Dashboard
  • C. iLO Amplifier Pack
  • D. HPE Composer

Answer: C

Explanation:
References: https://www.slideshare.net/Xylos/hpe-infosight-for-servers

NEW QUESTION 5
Match each HPE server platform with optimal workload.
HPE0-S58 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
HPE0-S58 dumps exhibit

NEW QUESTION 6
An integrator has installed a new Synergy frame into a rack with two existing Synergy frames in a customer’s environment.
Click where the integrator should verify that the cabling for the management ring was completed correctly.
HPE0-S58 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
HPE0-S58 dumps exhibit

NEW QUESTION 7
Which component of the HPE Synergy solution should you use to set the firmware/driver baseline and the installation method for Synergy Compute nodes?

  • A. Composer
  • B. Smart Update
  • C. Image Streamer
  • D. Global Dashboard

Answer: B

Explanation:
References: https://support.hpe.com/hpsc/doc/public/display?docId=c05212310

NEW QUESTION 8
How can an integrator use an HPE Synergy D3940 storage module to provision shared storage to compute modules without requiring a separate SAN to be connected to the frame?

  • A. Configure drives as DAS storage, and use Image Streamer to present the disks as iSCSI targets to the whole frame.
  • B. Configure drives as SAN storage, and configure a Smart Array P416ie-m Controller into HBA mode.Add the SAN disk to the server profile.
  • C. Configure drives as DAS storage, and use StoreVirtual VSA to present the disks as iSCSI storage to the whole frame.
  • D. Configure drives as SAN storage, and configure a P240nr array controller into HBA mod
  • E. Add the SAN disk to the server profile.

Answer: C

Explanation:
References: https://www.iistech.com/blog/composable-infrastructure-with-hpe-synergy-part-2

NEW QUESTION 9
A customer needs to aggregate uplink ports from two Virtual Connect interconnects to increase bandwidth and availability of the networks configured for HPE Synergy platform.
Which steps must the integrator perform in the configuration to meet the customer’s needs?

  • A. Connect Satellite modules using Ports L1 and L4
  • B. Connect Ports Q7 and Q8 on the Master interconnect Modules (ICM)
  • C. Install Redundant Frame Link Modules and a second management ring
  • D. Enable Intelligent Resilient Fabric (IRF) on the Virtual Connect Modules

Answer: A

NEW QUESTION 10
A customer needs to attach 20 HPE 1 TB SATA 6G SFF hard drives to an HPE Synergy 480 Gen10 compute module.
Which HPE products are necessary to meet the requirements? (Choose three.)

  • A. HPE D3940 storage module
  • B. HPE Synergy 12Gb SAS Connection Module
  • C. HPE 10GbE SynergyPass-Thru Module
  • D. HPE Smart Array P416ie-m Controller
  • E. HPE Smart Array P542D Controller

Answer: BDE

NEW QUESTION 11
In a 3-frame HPE Synergy environment, how should an integrator place the image Streamer modules to allow for redundancy to all of the management connections?

  • A. one Image Streamer module in frame 2, and a second Image Streamer Module in frame 3 (2 total)
  • B. two Image Streamer modules in frame 2, and two Image Streamer modules in frame 3 (4 total)
  • C. one Image Streamer module in each Synergy frame (3 total)
  • D. two Image Streamer modules in frame 1 (2 total)

Answer: B

NEW QUESTION 12
Refer to the exhibit.
HPE0-S58 dumps exhibit
A customer with the design shown needs to perform an in-place upgrade to its environment to scale the two-frame single homed Multimodule Link Aggregation Group (MLAG) configuration to a three-frame
configuration. The new frame needs to provide a redundant 20Gb connection for the compute module ports in Fabric 3.
Which interconnect modules should the integrator use in Frame 3?

  • A. HPE Virtual Connect SE 40Gb F8 module in bay 3 and HPE Virtual Connect SE 40Gb F8 Module in bay 6
  • B. HPE Synergy 10Gb Interconnect Link Module in bay 3 and HPE Synergy 10Gb Interconnect Link Module in bay 6
  • C. HPE Synergy 20Gb Interconnect Link Module in bay 3 and HPE Synergy 20Gb Interconnect Link Module in bay 6
  • D. HPE Synergy 20Gb Interconnect Link Module in bay 3 and HPE Synergy 10Gb Interconnect Link Module in bay 6

Answer: B

NEW QUESTION 13
Which management tool required by HPE Infosight must be deployed at the customer site?

  • A. HPE Global Dashboard
  • B. HPE OneView
  • C. HPE iLO Amplifier
  • D. HPE StoreServ Management Console (SSMC)

Answer: C

NEW QUESTION 14
A customer requires all automated Fibre Channel zones to have a prefix of “SYNERGY” in the automatically-generated zones.
Click where the integrator should change the naming policy.
HPE0-S58 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
HPE0-S58 dumps exhibit

NEW QUESTION 15
A customer has forgotten the password for the HPE Composer managing the customer’s HPE Synergy Infrastructure.
Where can the customer reset the password with the assistance of HPE Support?

  • A. FLM Access to Synergy Console
  • B. Virtual Center server
  • C. Front Access Panel to Synergy Console
  • D. Maintenance Console screen

Answer: A

Explanation:
References:
https://support.hpe.com/hpsc/doc/public/display?docId=emr_na-a00028780en_us&docLocale=en_US

NEW QUESTION 16
During an initial setup of a Synergy environment, an integrator needs to enable or disable authorized Service access.
What will be the outcome when the integrator disables this service?

  • A. Authenticated administrators will be unable to make changes to the system
  • B. Authorized users will be unable to generate a support dump
  • C. Authenticated administrators will be unable to access the system
  • D. Authorized support will be unable to diagnose the system

Answer: D

NEW QUESTION 17
Refer to the exhibit.
HPE0-S58 dumps exhibit
How should an integrator pair interconnect bays to set up redundant fabrics in an HPE Synergy 12000 Frame?

  • A. Interconnect bays 1 and 2; bays 3 and 4; bays 5 and 6.
  • B. Interconnect bays 1 and 6; bays 2 and 5; bays 3 and 4.
  • C. Interconnect bays 1 and 4; bays 2 and 5; bays 3 and 6.
  • D. Interconnect bays 1 and 3; bays 2 and 4; bays 5 and 6.

Answer: C

NEW QUESTION 18
A customer has a Hyper-V and ESXi hypervisors deployed on an HPE Synergy platform. The customer needs a tool that will provide health and performance monitoring. Because their environment is very dynamic, the tool should also help them to optimize performance and predict and prevent problems.
Which tool should the customer use?

  • A. HPE InfoSight
  • B. HPE OneView for vCenter Server
  • C. HPE Composer
  • D. HPE Global Dashboard

Answer: C

NEW QUESTION 19
Refer to the exhibit.
HPE0-S58 dumps exhibit
A customer has an HPE Synergy 2-frame configuration, as shown. The customer has a new project and needs to increase the number of compute modules.
What is the maximum number of compute nodes that the customer’s fabric could support?

  • A. 24
  • B. 36
  • C. 48
  • D. 60

Answer: D

NEW QUESTION 20
What does the hypervisor cluster profile feature of HPE OneView enable the integrator to accomplish?

  • A. configure a DRS cluster that provides load balancing functionality
  • B. enable Adaptive Optimization using SSMC that will optimize VM location
  • C. enable load balancing policies for the most important VMs using vCenter Server and traffic shaping policies
  • D. use the CPU affinity option to improve CPU scheduling

Answer: A

NEW QUESTION 21
......

Recommend!! Get the Full HPE0-S58 dumps in VCE and PDF From Certshared, Welcome to Download: https://www.certshared.com/exam/HPE0-S58/ (New 97 Q&As Version)