It is more faster and easier to pass the PRINCE2-Exams PRINCE2-Practitioner exam by using Download PRINCE2-Exams PRINCE2 Practitioner exam questuins and answers. Immediate access to the Rebirth PRINCE2-Practitioner Exam and find the same core area PRINCE2-Practitioner questions with professionally verified answers, then PASS your exam with a high score now.

Online PRINCE2-Practitioner free questions and answers of New Version:

NEW QUESTION 1
HOTSPOT
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion
caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions. Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract. Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Prince2-Practitioner dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
Prince2-Practitioner dumps exhibit

NEW QUESTION 2

Which of the following is not part of the composition of a Plan?

  • A. Pre-requites
  • B. Assumptions
  • C. Quality responsibilities
  • D. Product descriptions

Answer: C

NEW QUESTION 3

There are two time driven controls in PRINCE2, which are they?

  • A. Highlight and End Stage Reports
  • B. Highlight and Checkpoint Reports
  • C. Checkpoint and End Project Reports
  • D. Highlight and Lessons Reports

Answer: B

NEW QUESTION 4

During which process would the stage tolerances be set?

  • A. Controlling a Stage
  • B. Initiating a Project
  • C. Managing a Stage Boundary
  • D. Directing a Project

Answer: D

NEW QUESTION 5

Which of the following should NOT be included in the business case?

  • A. Reasons
  • B. Major Risks
  • C. Business options
  • D. Business approach

Answer: D

NEW QUESTION 6

Additional Information Product Description
Prince2-Practitioner dumps exhibit
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Quality standards section?

  • A. Delete entry 4 because external suppliers are responsible for applying any relevant standards to their work.
  • B. Delete entry 5 because the lack of a change management procedure makes the MFH document standards unsuitable.
  • C. Add 'All contracts must conform to current employment laws".
  • D. Add 'PRINCE2 change control procedures will be used to manage any changes to baselined products'.

Answer: C

NEW QUESTION 7

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.
Prince2-Practitioner dumps exhibit
Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?

  • A. Delete entry 9 because activities for controlling the project should be planned as part of Project controls in the Project Initiation Documentation.
  • B. No change to entry 9 because it describes the timing of performance reports.
  • C. Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.

Answer: B

NEW QUESTION 8

Which of the following activities could trigger the production of an exception plan?

  • A. Review Stage status
  • B. Giving ad hoc direction
  • C. Escalating a project issue
  • D. Report stage end

Answer: B

NEW QUESTION 9

Which statement is TRUE with regard to technical stages?

  • A. Technical stages can only occur sequential
  • B. Technical stages define where management decisions are appropriate
  • C. Technical stages often overlap
  • D. Technical stages define the commitment of resources and authority to spend

Answer: C

NEW QUESTION 10

Which statement best explains the purpose of Tailor to suit the project environment?

  • A. Ensure project controls are based on project's scale, complexity, importance, capability and risk
  • B. To use a set of pre-defined templates for the size of project
  • C. To tailor the use of the principles to suit the project
  • D. To pick which PRINCE2 processes to apply and which to leave out

Answer: D

NEW QUESTION 11

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?

  • A. Benefits Review Plan
  • B. Exception Report
  • C. End Project Report
  • D. Risk Register

Answer: C

NEW QUESTION 12

Additional Information Product Description
Prince2-Practitioner dumps exhibit
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.

  • A. Obtain agreement from the Director of Facilities Division to redesign the service level agreement within the remaining +2 days tolerance.
  • B. Raise an issue (off-specification).
  • C. Accept this error as a concession.
  • D. No action required.

Answer: D

NEW QUESTION 13

Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions. Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract. Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10
years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Timescale heading?

  • A. The contract with the selected service provider will be agreed during stage 3.
  • B. The expected benefits will be calculated over 10 years from completion of the project.
  • C. If more MFH divisions are added to the scope of the services to be outsourced, the project timescale will be extended and the realization of benefits will be delayed.
  • D. The expected benefits should start to be realized as soon as the outsourced services become operational at the end of stage 4.
  • E. The transfer of equipment and staff is estimated to take six weeks.

Answer: AB

NEW QUESTION 14

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Risk management procedure heading?

  • A. When a new problem arises, a full impact analysis will be undertaken to assess the impact on the project' objectives and Business Case.
  • B. Probability will be assessed against the scales defined in this Risk Management Strategy.
  • C. Any risk which has an expected value of more than £1 k will NOT be registered.
  • D. Every threat and opportunity identified must be clearly defined in terms of cause, event and effect.
  • E. 'Reduce' Response actions which result in a lower impact and/or probability rating.

Answer: BD

NEW QUESTION 15

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
What additional risk will this place on the project?

  • A. None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.
  • B. These changes will delay stage 3 by three weeks.
  • C. There is only £70k left in the project change budget.
  • D. The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.

Answer: A

NEW QUESTION 16
......