Q61. -(Topic 1)
You need to recommend a solution to remediate the Exchange Server 2010 service failures. The solution must meet the technical requirements.
What should you include in the recommendation?
A. Create a service request workflow that triggers a dependent activity.
B. Create an incident event workflow that triggers a dependent activity.
C. Create an incident event workflow that triggers a runbook activity.
D. Create a service request workflow that triggers a runbook activity.
Answer: C
Q62. -(Topic 7)
Your company has a private cloud that contains a System Center 2012 infrastructure.
The network contains a Service Manager infrastructure and a Configuration Manager
infrastructure.
You create a configuration baseline for desired configuration management.
You need to ensure that an incident is created automatically in Service Manager when a device is non-compliant
You install the Configuration Manager connector for Service Manager.
What should you do next?
A. Create an incident template.
B. Import the Configuration Manager Management Packs.
C. Create a Desired Configuration Management Event Workflow Configuration.
D. Create a service level objective (SLO) for the desired configuration management incident.
Answer: C
Q63. DRAG DROP -(Topic 7)
Your company has a private cloud that is managed by using a System Center 2012 infrastructure.
The private cloud contains 200 servers that run Windows Server 2008 R2. All of the servers are managed by Operations Manager.
The private cloud contains an application named App1 that is deployed on-demand to several servers. The servers that run the application are identified by a registry value set during the application's installation.
You create a monitor that targets all of the servers.
You need to modify the monitor to only affect the servers that have the application installed.
Which three actions should you perform in sequence? (To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Answer:
Q64. -(Topic 5)
Topic 5, Contoso Ltd
Overview
Contoso, Ltd. is a manufacturing company that has 3,000 users.
Contoso has a data center in Toronto and 20 offices across Canada. The offices connect to
each other by using a WAN link. Each office connects directly to the Internet.
Existing Environment
Active Directory Environment
The network contains an Active Directory forest named contoso.com. The forest contains a single domain. All domain controllers run Windows Server 2012. All servers run Windows Server 2008 R2.
Each office contains three domain controllers. Each office is configured as an Active Directory site.
System Center 2012 Infrastructure
Contoso has a System Center 2012 infrastructure that contains 11 servers. The servers are configured as shown in the following table.
Contoso has a private cloud named Cloud1. Cloud1 is managed by using VMM. The
following applications run in Cloud 1:
. Microsoft Exchange Server 2010
. Microsoft SharePoint Server 2010
. A custom manufacturing application named App1
The Hyper-V hosts are managed by using VMM. TOR-H01 and TOR-H02 are nodes in a failover cluster.
The switches that are part of the network fabric are from various manufacturers and are managed by using SNMPv3.
App1
An application named App1 is deployed from a VMM service template that consists of one front-end web server and one back-end database server. App1 processes credit card
information.
The instance of App1 running in the data center uses two virtual machines named VM1 and
VM2. TOR-H01 hosts VM1 and VM2.
App1 is managed by using a custom management pack named MP1. The management
pack used to monitor App1 contains a distributed application diagram named App1DAD.
The service level agreement (SLA) for App1 states that App1 must be available 99 percent
of the time.
Problem Statements
Contoso identifies the following issues:
. Currently, all Operations Manager alerts are sent by email only. Database administrators require alerts to be sent by text message. The cell phone numbers of the database administrators are already configured in Operations Manager.
. Administrators report that the processor performance counters for the Hyper-V hosts display values that are lower than the actual load on the hosts.
Requirements
Business Goals
Contoso wants to minimize hardware and software costs, whenever possible.
Planned Changes
Contoso plans to add a new web server to the App1 service template. Traffic to the new web server will be load balanced with the existing web server by using a hardware load balancer.
Technical Requirements
Contoso identifies the following technical requirements for the planned deployment:
. Automatically apply software updates issued by Microsoft to all of the Hyper-V hosts.
. Automatically assign incidents to administrators when a Configuration Manager service fails.
. Ensure that the Exchange Server administrators can request that new virtual machines be added to the Exchange Server organization by using Internet Explorer.
. Monitor the uptime of all the Hyper-V hosts and all the virtual machines by using Operations Manager and VMM. Performance and Resource Optimization (PRO)-enabled management packs will be used.
. Ensure that users have a self-service portal that provides them with the ability to back up individual virtual machines. Users must receive an email message confirming that the backup is complete.
. Ensure that database administrators are alerted by a text message when an error occurs on a server that they manage. The text messages should be delivered regardless of the current network conditions.
. Network administrators report that they currently use different tools to monitor the port status on the switches. The network administrators want to manage all of the switches by using Operations Manager.
App1 Requirements
Contoso identifies the following requirements for App1:
. Create an object in the App1 management pack to track the SLA.
. Ensure that multiple monitoring thresholds can be used for different instances of App1.
. Ensure that App1 complies with the Payment Card Industry Data Security Standard (PCI DSS).
You need to recommend a solution to meet the technical requirements for MP1.
What should you include in the recommendation? (More than one answer choice may achieve the goal. Select the BEST answer.)
A. Aggregate rollup monitors
B. Event collection rules
C. Synthetic transactions
D. Overrides
Answer: D
Q65. -(Topic 5)
You need to recommend a solution to meet the update requirement for the Hyper-V hosts.
What should you include in the recommendation? (More than one answer choice may achieve the goal. Select the BEST answer.)
A. System Center 2012 Orchestrator runbooks
B. VMM update baselines
C. System Center 2012 Service Manager workflows
D. Configuration Manager auto deployment rules
Answer: B
Q66. -(Topic 4)
You need to recommend a solution to meet the technical requirements for incident resolution.
What should you recommend? (More than one answer choice may achieve the goal. Select the BEST answer.)
A. From Service Manager, create a custom management pack.
B. From Operations Manager, auto resolve alerts.
C. From Operations Manager, configure the Alert Sync connector.
D. From Service Manager, create an Incident Management workflow.
Answer: A