Latest PMI Agile Certified Practitioner (PMI-ACP)® PMI-ACP Exam Engine
Exam Code: PMI-ACP (Practice Exam Latest Test Questions VCE PDF)
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)®
Certification Provider: PMI
Free Today! Guaranteed Training- Pass PMI-ACP Exam.
PMI PMI-ACP Free Dumps Questions Online, Read and Test Now.
NEW QUESTION 1
How does Empirical Process Control support Agile methodologies?
- A. Testing, requirements, and adaptation
- B. Testing, requirements, and change
- C. Visibility, review, and testing
- D. Visibility, inspection, and adaptation
Answer: D
NEW QUESTION 2
What is the first thing that a team should do to estimate user stories for a project?
- A. Sort the user stories according to priority.
- B. Schedule a team meeting to understand them.
- C. Define the story points measure.
- D. Estimate through function point analysis.
Answer: C
NEW QUESTION 3
Which of the following is critical for the success of distributed Agile teams?
- A. Cost containment
- B. High volume of communication
- C. Shared knowledge
- D. Culture of collaboration
Answer: D
NEW QUESTION 4
When developing user stories, user expectations are best captured in what form?
- A. Acceptance tests
- B. Entrance criteria
- C. Done criteria
- D. Go and no-go limits
Answer: A
NEW QUESTION 5
Which of the following is an example of a visual aid used in Lean-Agile software development?
- A. Business value delivered chart
- B. Product technical specifications
- C. Automated code coverage report
- D. Scrum-of-Scrum report
Answer: A
NEW QUESTION 6
Estimating costs for an Agile project starts with which of the following types of meetings?
- A. Project Retrospective
- B. Steering Committee
- C. Release Planning
- D. Sprint Planning
Answer: C
NEW QUESTION 7
What is the responsibility of an extreme Programming (XP) customer role?
- A. Testing the daily increments of the software developed
- B. Writing the stories and acceptance tests for each story
- C. Planning and task allocation for the developer and tester
- D. Interacting closely with users and representing the XP team
Answer: B
NEW QUESTION 8
When are acceptance tests typically written for a user story?
- A. After coding the story, but before user acceptance testing begins
- B. After writing the story, but before coding begins
- C. At the start of Product Backlog prioritization planning
- D. After estimating the Product Backlog, but before Sprint planning begins
Answer: C
NEW QUESTION 9
What is the role in an eXtreme Programming (XP) project that ensures the right project
processes are applied?
- A. Domain Expert
- B. Product Owner
- C. ScrumMaster
- D. Coach
Answer: D
NEW QUESTION 10
Applying the Pareto rule when prioritizing the Product Backlog means that:
- A. features that are lower priority are more likely to slip to the next iteration.
- B. the value of a feature is not realized until the feature is complete.
- C. more recent requests are usually more important to the business.
- D. a small percentage of the work will provide a large percentage of the value.
Answer: D
NEW QUESTION 11
The purpose of a project burndown chart is to:
- A. Identify and communicate upcoming milestones.
- B. Display the level of effort and resources utilized.
- C. Identify dependencies between sprints or iterations.
- D. Display the remaining work across time.
Answer: D
NEW QUESTION 12
A “Scrum of Scrums” meeting is:
- A. Another name for the daily standup project meeting in a Scrum team.
- B. Amechanism that coordinates multiple teams working on a single project.
- C. Aproject meeting that happens twice every day across the Scrum teams.
- D. An occasional leadership meeting that provides direction to multiple Scrum teams.
Answer: B
NEW QUESTION 13
In an Agile approach, project values are most effectively implemented when they are determined by the:
- A. sponsor
- B. team
- C. project manager
- D. methodology
Answer: B
NEW QUESTION 14
Who is responsible for determining the business value of each feature?
- A. Product Owner
- B. Steering committee
- C. ScrumMaster
- D. Team
Answer: A
NEW QUESTION 15
A ScrumMaster:
- A. prioritizes the work for each iteration.
- B. directs the activities of the team.
- C. provides leadership, guidance, and coaching.
- D. manages the project scope and budget.
Answer: C
NEW QUESTION 16
In the Lean process, the focus is on:
- A. Managing team efficiency.
- B. Optimizing completed work across the process stream.
- C. Using the optimal resources.
- D. Cross training the team to eliminate bottlenecks.
Answer: B
NEW QUESTION 17
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can inferthat:
- A. Work was removed from the Product Backlog.
- B. Work was added to the Product Backlog.
- C. The team's velocity increased.
- D. The team's velocity decreased.
Answer: B
NEW QUESTION 18
When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?
- A. Stop work on unfinished user stories and work on the urgent request.
- B. Call a team meeting and change the iteration scope to include the request.
- C. Provide the customer with options provided by the project team.
- D. Explain that the team cannot do the added work until the next iteration.
Answer: C
100% Valid and Newest Version PMI-ACP Questions & Answers shared by 2passeasy, Get Full Dumps HERE: https://www.2passeasy.com/dumps/PMI-ACP/ (New 145 Q&As)