Review MB5-705, individuals name because Managing Microsoft Dynamics Implementations. MB5-705 audit is usually a wonderful qualifications of IT that is certainly required by means of many IT industry experts when traveling high list and also high level of know-how inside their useful specialized niche. Certification connected with Review MB5-705 gives you evident opportunities of having superior position and also career. By getting Microsoft MB5-705 qualifications you can elevate your worth and also benefit when in front of your current business employers.
Q31. Which activity is associated with planning communication management?
A. assigning the project team
B. conducting team meetings
C. developing the project schedule
D. conducting the kickoff meeting
Answer: D
Q32. During your requirements and process review, you use the questionnaires provided by Sure Step. What is one of the reasons that you use the questionnaire at this stage?
A. to assist in determining the budget of the project
B. to use as a tool by the partner prior to meeting with the customer
C. to create detailed process maps
D. to use as a checklist and a reminder of topics to investigate
Answer: D
Explanation: http://technet.microsoft.com/en-us/library/aa569899.aspx A questionnaire is a set of questions that is used to collect information for variety of purposes. You can design, create, distribute, and complete questionnaires, and then analyze the results. You can customize a questionnaire to fit your specific needs by using a combination of the various features that are available in Microsoft Dynamics AX. For example, questionnaires can be used to:
Test the professional skills of employees and applicants.
Test course participants at the end of the course.
Evaluate a course, including facilities, content, and instructor.
Survey employee and customer satisfaction.
Evaluate employee job performance.
The following table provides links to information about the core questionnaire tasks.
.....
Q33. What is an objective of diagnostic preparation?
A. to lead an internal kickoff meeting
B. to gain a preliminary understanding of the customer's needs
C. to plan the running of diagnostic accelerators
D. to prepare high-level project documents
Answer: B
Explanation: http://technet.microsoft.com/en-us/library/aa496439.aspx
Q34. You need to create a proposal for the final licensing and services agreement.
Which two roles should be involved in creation of the proposal? (Each correct answer presents part of the solution. Choose two.)
A. account manager
B. project manager
C. sales representative
D. engagement manager
Answer: B,D
Explanation: B: Project Manager: The project manager is what the name suggests:the project manager. Heor shekeeps the project running, allocates resources, maintains the project plan, work break down structure and is the contact person for the Customers project manager. The Project manager has a representative function and coordinates meetings withseveralteam members
D: Engagement Manager: The Engagement Manager participates only in the starting phase of a project. He is responsible to transfer a sales project into animplementation project.
* Final Licensing and Services Agreement is an activity that you execute acrossmany phases of the project. The purpose of the activity in the Diagnostic phase isto document the overall scope of the implementation and gain the agreement ofthe customer. This activity produces two key deliverables:
. The Statement of Work (SOW), which details the scope of theimplementation. . The Budgetary Estimate Proposal, which provides details of the costcomponents.
The key benefits gained by performing this activity are:
. A presentation and walk through of the SOW and Budgetary Estimate Proposal.
. The opportunity for the customer to review and provide feedback onthe SOW and Budgetary Estimate Proposal before acceptance. http://technet.microsoft.com/en-us/aa699451.aspx
Q35. The diagnostic phase includes which two deliverables? (Each correct answer presents part of the solution. Choose two.)
A. risk and issues register
B. high-level project charter
C. solution design document
D. statement of work
Answer: B,D
Explanation: Diagnostic Phase Purpose To gather enough information to define the high-level project charter and make a confident proposal for the implementation phases. The Diagnostic phase startsduring the sales process and ends with an accepted proposal and statement of work (SOW) for the next part of the implementation project. The major deliverablefor this phase is the SOW and the Budgetary Estimate Proposal.
Deliverables
(B)
High-Level Project Charter High-Level Project Plan
(D)
Statement of Work Budgetary Estimate Proposal [Optional] Decision Accelerator Deliverables, including Customer Reports Milestones Customer accepts the SOW and the Budgetary Estimate Proposal, including the high-level project charter and high-level project plan. http://technet.microsoft.com/en-us/library/aa496439.aspx
Q36. During which phase of a waterfall delivery is the creation and delivery of a complete system configuration performed?
A. data migration
B. development
C. design
D. analysis
Answer: B
Explanation: http://en.wikipedia.org/wiki/Waterfall_model http://blogs.msdn.com/b/dpe_nigeria/archive/2012/06/13/new-tfs-template-available-quot-agile-dev-in-a-waterfall-environment-quot-govdev.aspx
Q37. As a project manager, you need to ascertain which human resources are involved in the
project and Fit Gap documents on the Decision Accelerators.
Which two Microsoft Dynamics Sure Step Methodology tree nodes provide this information for the implementation project? (Each correct answer presents part of the solution. Choose two.)
A. Solution Envisioning
B. Resources
C. Roles
D. Deliverables
E. PExplanation: References
Answer: B,C
Explanation: Explanation: References: http://download.microsoft.com/download/3/a/c/3ac11404-03a8-4d55-9b90-f789286a4f34/Fit_Gap_Datasheet.pdf http://vjeko.com/blog/fit-gap-and-solution-blueprint-estimates http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx http://technet.microsoft.com/en-us/library/aa496439.aspx
Q38. You need to createaproject management diamond.
Which constraints should you use at each corner?
A. cost, quality, scope, risk
B. expectations, scope, time, risk
C. cost, expectations, scope, time
D. cost, quality, scope, time
Answer: D
Explanation: Reference:http://en.wikipedia.org/wiki/File:PM_DiamondModel.jpg
Q39. On the “Add new project data” window, choose a Solution, Product, and Engagement Type. Type your project name and optionally fill in the rest of the fields. Click Next to continue.
Etc.
http://blogs.msdn.com/b/ukax/archive/2012/01/10/sure-step-online-project-wizard.aspx
Q40. You need to perform end-user training in the deployment phase.
What are two types of trainers you can use? (Each correct answer presents part of the solution. Choose two.)
A. specialized
B. deployment
C. customer
D. production
Answer: A,C
Explanation: A: Some areas of the solution might need high-level specialized trainers.
C: This training can be conducted by customer key users, trainers, or consultants of the consulting implementation team, or by an external third-party vendor.
http://technet.microsoft.com/en-us/library/aa496439.aspx