Microsoft official certifications, which unfortunately possess optimum importance there employment market, might avert "pirate talent" having its highly-priced fee together with stringent enlisting program, especially the course regarding exercise, secure the trainees to master an item warranted together with keep its original "solid attribute.Inches The strictness associated with Microsoft official certifications will be world-famous together with whoever has purchased a qualification got been given typically 3 to 4 instances schooling. Today, there does exist also virtually no a document you who may have surpassed a official certifications analyze only will be experienced finally.
Q1. As a project manager, you need to incorporate a change request into the project.
Which two tasks must be completed to correctly handle this request when you use the Microsoft Dynamics Sure Step Methodology? (Each correct answer presents part of the solution. Choose two.)
A. Complete a customer review and approval.
B. Complete a plan-do-check-act cycle.
C. Complete a change request form.
D. Complete a work breakdown structure.
E. Complete a risk identification.
Answer: A,C
Explanation: http://technet.microsoft.com/en-us/library/hh227544.aspx
Q2. You are responsible for using the Sure Step Project Creation Wizard to create projects that involve multiple products, Decision Accelerators, and project types.
Which constraint do you need to consider?
A. A project can contain multiple Decision Accelerators.
B. A project can contain multiple products.
C. A project can be associated with multiple project types.
D. The project repository can only contain 100 active projects at a time.
Answer: A
Q3. You are a project manager for Contoso Ltd, an e-commerce company.
Contoso's Microsoft Dynamics implementation project is in the deployment phase, and you are planning the user acceptance testing.
Which action should be the focus of the testing?
A. testing the performance to ensure the system can handle the predicted peak time transaction volumes
B. testing that the system supports the company's transaction data
C. testing data migration
D. testing the end-to-end system to ensure the system supports the company's transactions
Answer: D
Explanation: Chapter 5 - Stabilizing Phase http://technet.microsoft.com/en-us/library/bb497042.aspx
Q4. Go live is complete, and you are now in theoperation phase of the project.
Which two activities can be performed in the operations phase? (Each correct answer presents part of the solution. Choose two.)
A. Document lessons learned.
B. Review deliverables against the statement of work (SOW).
C. Perform end-user training.
D. Conduct production audit.
Answer: A,B
Explanation: B: You can find the following activities in the Operations phase: /Project Planning / Provide Post Go Live Support / Transition of Solution to Support / (B) Review Deliverables against SOW and Agreed Changes / Conduct Performance Tuning and Optimization
A: Project Planning
The purpose of the Project Planning activity in the Operations phase is to closethe project
after Go-Live and complete final project tasks.
You want to make sure that you delivered as promised, and that the customer is satisfied
with the project outcome. This activity consists of the following tasks:
/ Finalize the project plan to accurately reflect the timeline, resourcesand milestones
completed.
/ Complete the final project activities required to complete asuccessful closure of the
project, such as:
(A) Document lessons learned.
Finish any documentation promised to the customer in the statement of work (SOW)
Determine the need for and conducting additional end-user training, if it is required.
Perform a final knowledge transfer to the customer
Clear any pending items that are discovered before, during, andafter Go-Live.
http://technet.microsoft.com/en-us/library/aa496439.aspx
Q5. You are responsible for creating and managing projects in a project repository.
Which two actions can you perform on existing projects in the repository? (Each correct answer presents part of the solution- Choose two.)
A. clone a project
B. share a project
C. change a project type
D. delete a project
Answer: A,D
Explanation: The project properties tab is also used to create new projects, clone projects, and delete projects.
http://blogs.msdn.com/b/project/archive/2007/02/24/deliverables.aspx
Q6. You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft Dynamics products for your customers.
Your customer's major stakeholders identify significant changes that will increase the scope of a project.
Which two risk response strategies for the project definition update should you use? (Each correct answer presents part of the solution, Choose two.)
A. Exploit
B. Avoid
C. Enhance
D. Transfer
E. share
Answer: B,D
Q7. Which two tasks can you perform from both the Microsoft Dynamics Sure Step Client on-premise application and the Sure Step Online application? (Each correct answer presents part of the solution. Choose two.)
A. Create and save project repositories the same as they are saved by using the Microsoft Dynamics Sure Step Client Project Creation Wizard.
B. Import a Sure Step project.
C. Access the lists of document templates in the Documents menu.
D. Clone a Sure Step project.
E. Navigate the Explanation: Reference material in the Methodology menu.
Answer: C,E
Q8. You are the project manager for a Microsoft Dynamics implementation for a new customer.
You need to ensure the finalization of the engagement proposal for the project.
Which person is responsible for managing the receipt of information for the proposal?
A. the engagement manager
B. the project manager
C. the sales representative
D. the account manager
Answer: A
Q9. You are performing a Decision Accelerator Offering. In which order should you perform the steps?
A.
1.
Meet internally to discuss the Decision Accelerator Offering
2.
Meet with the customer to discuss the Decision Accelerator Offering
3.
Review the presentation and customer sign-off
4.
Perform activities
B.
1.
Meet with the customer to discuss the Decision Accelerator Offering
2.
Meet internally to discuss the Decision Accelerator Offering
3.
Perform activities
4.
Review the presentation and customer sign-off
C.
1.
Meet with the customer to discuss the Decision Accelerator Offering
2.
Meet internally to discuss the Decision Accelerator Offering
3.
Review the presentation and customer sign-off
4.
Perform activities
D.
1.
Meet internally to discuss the Decision Accelerator Offering
2.
Meet with the customer to discuss the Decision Accelerator Offering
3.
Perform activities
4.
Review the presentation and customer sign-off
Answer: A
Explanation: http://download.microsoft.com/download/4/3/D/43D4FED9-54DC-4B3B-95B6-B17A15D1CB8F/03-DA-CRM_Datasheet_Oct-2011.pdf http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx http://technet.microsoft.com/en-us/library/aa496439.aspx
Q10. Which two statements differentiating projects from operational work are correct? (Each correct answer presents part of the solution. Choose two.)
A. The purpose of a project is to create a unique product, service, or result; the purpose of operations is to sustain the customer's business.
B. The duration of a project is temporary; the duration of operational work is ongoing.
C. The output of a project is variable; the output of operational work is continuous, daily, and predictable.
D. The purpose of a project is to sustain the new business requirements; operations end with the adoption of a new set of objectives, and then the work continues.
E. a project ends when it is replaced by a new process; operations end when its specific objectives have been attained.
Answer: A,B
Explanation: http://social.technet.microsoft.com/wiki/contents/articles/18503.implement-microsoft-dynamics-nav.aspx