Master the PMI-001 Project Management Professional content and be ready for exam day success quickly with this Testking PMI-001 download. We guarantee it!We make it a reality and give you real PMI-001 questions in our PMI PMI-001 braindumps.Latest 100% VALID PMI PMI-001 Exam Questions Dumps at below page. You can use our PMI PMI-001 braindumps and pass your exam.

Check PMI-001 free dumps before getting the full version:

NEW QUESTION 1
Which is an input to the Verify Scope process?

  • A. Performance report
  • B. Work breakdown structure (WBS)
  • C. Requested changes
  • D. Project management plan

Answer: D

NEW QUESTION 2
Which Process Group typically consumes the bulk of a project's budget?

  • A. Monitoring and Controlling
  • B. Executing
  • C. Planning
  • D. Initiating

Answer: B

NEW QUESTION 3
The product scope description is used to: A. Gain stakeholders' support for the project.

  • A. Progressively elaborate the characteristics of the product, service, or resul
  • B. Describe the project in great detai
  • C. Define the process and criteria for accepting a completed product, service, or resul

Answer: B

NEW QUESTION 4
What are the identified risks for doingexcessive decomposition in a WBS?

  • A. Insufficient project funding and disqualification of sellers
  • B. Insufficient project funding and ineffective use of resources
  • C. Disqualification of sellers and non-productive management efforts
  • D. Non-productive management effort and inefficient use of resources

Answer: D

NEW QUESTION 5
The Process Group that involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan is known as:

  • A. Initiatin
  • B. Plannin
  • C. Executin
  • D. Monitoring and Controllin

Answer: C

NEW QUESTION 6
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

  • A. Human resource management pla
  • B. Activity resource requirement
  • C. Personnel assessment tools,
  • D. Multi-criteria decision analysi

Answer: A

NEW QUESTION 7
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

  • A. Collaboration
  • B. Negotiation
  • C. Decision making
  • D. Influencing

Answer: D

NEW QUESTION 8
An input of the Create WBS process is:

  • A. requirements documentatio
  • B. scope baselin
  • C. project charte
  • D. validated deliverable

Answer: A

NEW QUESTION 9
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

  • A. lead
  • B. lag
  • C. mandatory dependency
  • D. internal dependency

Answer: A

NEW QUESTION 10
Analogous cost estimating relies on which of the following techniques?

  • A. Expert judgment
  • B. Project management software
  • C. Vendor bid analysis
  • D. Reserve analysis

Answer: A

NEW QUESTION 11
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

  • A. Initiating
  • B. Planning
  • C. Executing
  • D. Closing

Answer: C

NEW QUESTION 12
During which process group is the quality policy determined?

  • A. Initiating
  • B. Executing
  • C. Planning
  • D. Controlling

Answer: C

NEW QUESTION 13
Lessons learned documentation is gathered during which of the following Project Management Process Groups?

  • A. Planning
  • B. Executing
  • C. Closing
  • D. Initiating

Answer: C

NEW QUESTION 14
Which document in the project management plan can be updated in the Plan Procurement Management process?

  • A. Budget estimates
  • B. Risk matrix
  • C. Requirements documentation
  • D. Procurement documents

Answer: C

NEW QUESTION 15
Which of the following methods is a project selection technique?

  • A. Flowcharting
  • B. Earned value
  • C. Cost-benefit analysis
  • D. Pareto analysis

Answer: C

NEW QUESTION 16
The precedence diagramming method (PDM) is also known as:

  • A. Arrow Diagra
  • B. Critical Path Methodology (CPM).
  • C. Activity-On-Node (AON).
  • D. schedule network diagra

Answer: C

NEW QUESTION 17
......