NEW QUESTION 1
Which tool or technique is used in the Develop Project Management Plan process?

  • A. Pareto diagram
  • B. Performance reporting
  • C. SWOT analysis
  • D. Expert judgment

Answer: D

NEW QUESTION 2
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

  • A. Start-to-start (SS)
  • B. Start-to-finish (SF)
  • C. Rnish-to-finish (FF)
  • D. Finish-to-start (FS)

Answer: D

NEW QUESTION 3
Schedule milestones and a predefined budget are examples of:

  • A. Project constraint
  • B. Requirements documentatio
  • C. Organizational process asset
  • D. Activity cost estimate

Answer: A

NEW QUESTION 4
What are the key components of the communication model?

  • A. Encode, message and feedback-message, medium, noise, and decode
  • B. Encode, messaging technology, medium, noise, and decode
  • C. Sender, message and feedback-message, medium, noise, and translate
  • D. Receiver, message and feedback-message, medium, noise, and decode

Answer: A

NEW QUESTION 5
A weighting system is a tool for which area of Conduct Procurements?

  • A. Plan contracting
  • B. Requesting seller responses
  • C. Selecting seller's
  • D. Planning purchase and acquisition

Answer: C

NEW QUESTION 6
A regression line is used to estimate:

  • A. Whether or not a process is stable or has predictable performanc
  • B. How a change to the independent variable influences the value of the dependent variabl
  • C. The upper and lower specification limits on a control char
  • D. The central tendency, dispersion, and shape of a statistical distributio

Answer: B

NEW QUESTION 7
Who MUST know when a risk event occurs so that a response can be implemented?

  • A. Customers
  • B. Project sponsors
  • C. Project management team
  • D. Insurance claims department

Answer: C

NEW QUESTION 8
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?

  • A. Risk analysis
  • B. Risk tolerance
  • C. Risk management
  • D. Risk attitude

Answer: B

NEW QUESTION 9
Which of the following investigates the likelihood that each specific risk will occur?

  • A. Risk register
  • B. Risk audits
  • C. Risk urgency assessment
  • D. Risk probability and impact assessment

Answer: D

NEW QUESTION 10
What is project management?

  • A. A logical grouping of project management inputs, outputs, tools, and techniques
  • B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements
  • C. Launching a process that can result in the authorization of a new project
  • D. A formal, approved document that defines how the project is executed, monitored, and controlled

Answer: B

NEW QUESTION 11
Which item is an input to the Define Activities process?

  • A. Schedule data
  • B. Activity list
  • C. Risk register
  • D. Scope baseline

Answer: D

NEW QUESTION 12
A large portion of a projects budget is typically expended on the processes in which
Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing

Answer: B

NEW QUESTION 13
When would resource leveling be applied to a schedule model?

  • A. Before constraints have been identified
  • B. Before it has been analyzed by the critical path method
  • C. After it has been analyzed by the critical path method
  • D. After critical activities have been removed from the critical path

Answer: C

NEW QUESTION 14
Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?

  • A. Risk response planning
  • B. Manage stakeholders
  • C. Scope definition
  • D. Performance reporting

Answer: B

NEW QUESTION 15
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

  • A. Work performance informatio
  • B. Inspections and audit
  • C. Payment system
  • D. Procurement performance review

Answer: D

NEW QUESTION 16
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

  • A. Work breakdown structure
  • B. Organizational breakdown structure
  • C. Resource breakdown structure
  • D. Bill of materials

Answer: A