It is more faster and easier to pass the PMI PMI-001 exam by using Certified PMI Project Management Professional questuins and answers. Immediate access to the Down to date PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.

Online PMI-001 free questions and answers of New Version:

NEW QUESTION 1
Which of the following is an output of the Conduct Procurements process?

  • A. Project statement of work
  • B. Selected sellers
  • C. Risk register updates
  • D. Teaming agreements

Answer: B

NEW QUESTION 2
Progressively elaborating high-level information into detailed plans is performed by the:

  • A. project management office
  • B. portfolio manager
  • C. program manager
  • D. project manager

Answer: D

NEW QUESTION 3
The Plan Stakeholder Management process belongs to which Process Group?

  • A. Executing
  • B. Initiating
  • C. Planning
  • D. Monitoring and Controlling

Answer: C

NEW QUESTION 4
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  • A. Project team
  • B. Focus group
  • C. Change control board
  • D. Project stakeholders

Answer: C

NEW QUESTION 5
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

  • A. Bottom-up
  • B. Parametric
  • C. Analogous
  • D. Three-point

Answer: A

NEW QUESTION 6
Which type of analysis is used to develop the communications management plan?

  • A. Product
  • B. Cost benefit
  • C. Stakeholder
  • D. Research

Answer: C

NEW QUESTION 7
An output of the Plan Quality Management process is:

  • A. Aprocess improvement plan,
  • B. Quality control measurement
  • C. Work performance information,
  • D. The project management pla

Answer: A

NEW QUESTION 8
Plan-do-check-act is also known as:

  • A. prevention over inspectio
  • B. statistical samplin
  • C. management responsibility,
  • D. continuous improvemen

Answer: D

NEW QUESTION 9
The following is a network diagram for a project.
What is the critical path for the project?

  • A. A-B-D-G
  • B. A-B-E-G
  • C. A-C-F-G
  • D. A-C-E-G

Answer: C

NEW QUESTION 10
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

  • A. quality audits
  • B. process analysis
  • C. statistical sampling
  • D. benchmarking

Answer: A

NEW QUESTION 11
How is scheduled variance calculated using the earned value technique?

  • A. EV less AC
  • B. AC less PV
  • C. EV less PV
  • D. AC less EV

Answer: C

NEW QUESTION 12
Which baselines make up the performance measurement baseline?

  • A. Scope baseline, cost baseline, and schedule baseline
  • B. Scope baseline, project management baseline, and quality baseline
  • C. Cost baseline, schedule baseline, and risk baseline
  • D. Cost baseline, project management baseline, and schedule baseline

Answer: A

NEW QUESTION 13
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

  • A. stakeholder management strateg
  • B. communications management plan,
  • C. stakeholder register,
  • D. performance repor

Answer: A

NEW QUESTION 14
Cost aggregation is typically performed by aggregating work packages in accordance with the:

  • A. Program evaluation and review technique (PERT).
  • B. Cost of quality (COQ).
  • C. Rough order of magnitude (ROM).
  • D. Work breakdown structure (WBS).

Answer: D

NEW QUESTION 15
The total of the planned value (PV) is also known as:

  • A. work breakdown structure (WBS).
  • B. schedule targe
  • C. performance measurement baseline (PMB).
  • D. earned value baselin

Answer: C

NEW QUESTION 16
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  • A. Available organizational assets
  • B. Project staff assignments
  • C. Interpersonal skills
  • D. Enterprise environmental factors

Answer: A

NEW QUESTION 17
......