It is more faster and easier to pass the PMI PMI-001 exam by using Certified PMI Project Management Professional questuins and answers. Immediate access to the Down to date PMI-001 Exam and find the same core area PMI-001 questions with professionally verified answers, then PASS your exam with a high score now.
Online PMI-001 free questions and answers of New Version:
NEW QUESTION 1
Which of the following is an output of the Conduct Procurements process?
Answer: B
NEW QUESTION 2
Progressively elaborating high-level information into detailed plans is performed by the:
Answer: D
NEW QUESTION 3
The Plan Stakeholder Management process belongs to which Process Group?
Answer: C
NEW QUESTION 4
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
Answer: C
NEW QUESTION 5
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Answer: A
NEW QUESTION 6
Which type of analysis is used to develop the communications management plan?
Answer: C
NEW QUESTION 7
An output of the Plan Quality Management process is:
Answer: A
NEW QUESTION 8
Plan-do-check-act is also known as:
Answer: D
NEW QUESTION 9
The following is a network diagram for a project.
What is the critical path for the project?
Answer: C
NEW QUESTION 10
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
Answer: A
NEW QUESTION 11
How is scheduled variance calculated using the earned value technique?
Answer: C
NEW QUESTION 12
Which baselines make up the performance measurement baseline?
Answer: A
NEW QUESTION 13
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
Answer: A
NEW QUESTION 14
Cost aggregation is typically performed by aggregating work packages in accordance with the:
Answer: D
NEW QUESTION 15
The total of the planned value (PV) is also known as:
Answer: C
NEW QUESTION 16
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
Answer: A
NEW QUESTION 17
......
P.S. DumpSolutions.com now are offering 100% pass ensure PMI-001 dumps! All PMI-001 exam questions have been updated with correct answers: https://www.dumpsolutions.com/PMI-001-dumps/ (918 New Questions)