It is more faster and easier to pass the PMI CAPM exam by using Realistic PMI Certified Associate in Project Management (PMI-100) questuins and answers. Immediate access to the Latest CAPM Exam and find the same core area CAPM questions with professionally verified answers, then PASS your exam with a high score now.

NEW QUESTION 1

What does a CPI value greater than 1.0 indicate?

  • A. Cost right at the estimated value
  • B. Cost under the estimated value
  • C. Cost right at the actual value
  • D. Cost over the estimated value

Answer: B

NEW QUESTION 2

Which tool or technique is used to manage change requests and the resulting decisions?

  • A. Change control tools
  • B. Expert judgment
  • C. Delphi technique
  • D. Change log

Answer: A

NEW QUESTION 3

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

  • A. Bottom-up
  • B. Parametric
  • C. Analogous
  • D. Three-point

Answer: A

NEW QUESTION 4

Types of internal failure costs include:

  • A. inspections.
  • B. equipment and training.
  • C. lost business.
  • D. reworking and scrappin

Answer: D

NEW QUESTION 5

Lessons learned are created and project resources are released in which Process Group?

  • A. Planning
  • B. Executing
  • C. Closing
  • D. Initiating

Answer: C

NEW QUESTION 6

The process of identifying and documenting relationships among the project activities is known as:

  • A. Control Schedule.
  • B. Sequence Activities.
  • C. Define Activities.
  • D. Develop Schedul

Answer: B

NEW QUESTION 7

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

  • A. Estimate Costs
  • B. Estimate Activity Resources
  • C. Control Costs
  • D. Determine Budget

Answer: D

NEW QUESTION 8

An input to Develop Project Charter is a/an:

  • A. Business case.
  • B. Activity list.
  • C. Project management plan.
  • D. Cost forecas

Answer: A

NEW QUESTION 9

Change request status updates are an output of which process?

  • A. Perform Integrated Change Control
  • B. Direct and Manage Project Execution
  • C. Close Project or Phase
  • D. Monitor and Control Project Work

Answer: A

NEW QUESTION 10

The chart below is an example of a:
CAPM dumps exhibit

  • A. Responsibility assignment matrix (RAM)
  • B. Work breakdown structure (WBS)
  • C. RACI chart
  • D. Requirements traceability matrix

Answer: D

NEW QUESTION 11

What causes replanning of the project scope?

  • A. Project document updates
  • B. Project scope statement changes
  • C. Variance analysis
  • D. Change requests

Answer: D

NEW QUESTION 12

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

  • A. Push
  • B. Pull
  • C. Interactive
  • D. Iterative

Answer: B

NEW QUESTION 13

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

  • A. Initiating
  • B. Planning
  • C. Executing
  • D. Closing

Answer: C

NEW QUESTION 14

Which of the following characteristics are found in a functional organizational structure?

  • A. Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget
  • B. Limited project manager authority, limited resource availability, and a part-time project manager's role
  • C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role
  • D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Answer: A

NEW QUESTION 15

Conflict should be best addressed in which manner?

  • A. Early, in private, using a direct, collaborative approach
  • B. Early, in public, using an indirect, collaborative approach
  • C. Early, in private, using an indirect, cooperative approach
  • D. As late as possible, in public, using a direct, confrontational approach

Answer: A

NEW QUESTION 16

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

  • A. ends.
  • B. begins.
  • C. delays.
  • D. deviate

Answer: A

NEW QUESTION 17

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

  • A. Manage Stakeholder Expectations.
  • B. Monitor and Control Risks.
  • C. Plan Risk Management.
  • D. Report Performanc

Answer: A

NEW QUESTION 18

Success is measured by benefits realization for a:

  • A. strategic plan
  • B. project
  • C. portfolio
  • D. program

Answer: C

NEW QUESTION 19

Which is an example of Administer Procurements?

  • A. Negotiating the contract
  • B. Authorizing contractor work
  • C. Developing the statement of work
  • D. Establishing evaluation criteria

Answer: B

NEW QUESTION 20

Which tools or techniques are used in the Plan Schedule Management process?

  • A. Benchmarking, expert judgment, and analytical techniques
  • B. Statistical sampling, benchmarking, and meetings
  • C. Negotiations, pre-assignment, and multi-criteria decision analysis
  • D. Expert judgment, analytical techniques, and meetings

Answer: D

NEW QUESTION 21

Which of the following is an input to Direct and Manage Project Execution?

  • A. Requested changes
  • B. Approved change requests
  • C. Work performance information
  • D. Implemented defect repair

Answer: B

NEW QUESTION 22

Analytical techniques are a tool and technique of which process in Project Procurement Management?

  • A. Plan Procurement Management
  • B. Control Procurements
  • C. Conduct Procurements
  • D. Close Procurements

Answer: C

NEW QUESTION 23

When would resource leveling be applied to a schedule model?

  • A. Before constraints have been identified
  • B. Before it has been analyzed by the critical path method
  • C. After it has been analyzed by the critical path method
  • D. After critical activities have been removed from the critical path

Answer: C

NEW QUESTION 24

Which items are components of a project management plan?

  • A. Change management plan, process improvement plan, and scope management plan
  • B. Agreements, procurement management plan, and work performance information
  • C. Schedule management plan, project schedule, and resource calendars
  • D. Scope baseline, project statement of work, and requirements traceability matrix

Answer: A

NEW QUESTION 25

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

  • A. Histograms
  • B. Scatter diagrams
  • C. Flowcharts
  • D. Checksheets

Answer: D

NEW QUESTION 26

Which is an output from Distribute Information?

  • A. Earned value analysis
  • B. Trend analysis
  • C. Project records
  • D. Performance reviews

Answer: C

NEW QUESTION 27
......

P.S. prep-labs.com now are offering 100% pass ensure CAPM dumps! All CAPM exam questions have been updated with correct answers: https://www.prep-labs.com/dumps/CAPM/ (704 New Questions)