We provide real CAPM exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI CAPM Exam quickly & easily. The CAPM PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI CAPM dumps pdf and vce product and material, you can easily pass the CAPM exam.

Free demo questions for PMI CAPM Exam Dumps Below:

NEW QUESTION 1

In project management, a temporary project can be:

  • A. Completed without planning
  • B. A routine business process
  • C. Long in duration
  • D. Ongoing to produce goods

Answer: C

NEW QUESTION 2

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

  • A. Slack
  • B. Float
  • C. Lag
  • D. Lead

Answer: C

NEW QUESTION 3

Completion of the product scope is measured against the product:

  • A. prototypes
  • B. requirements
  • C. analyses
  • D. benchmarks

Answer: B

NEW QUESTION 4

The Plan Stakeholder Management process belongs to which Process Group?

  • A. Executing
  • B. Initiating
  • C. Planning
  • D. Monitoring and Controlling

Answer: C

NEW QUESTION 5

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  • A. Update
  • B. Preventive action
  • C. Defect repair
  • D. Corrective action

Answer: D

NEW QUESTION 6

Which tool or technique is effective in a project in which the deliverable is not a service or result?

  • A. Inspection
  • B. Variance analysis
  • C. Decomposition
  • D. Product analysis

Answer: D

NEW QUESTION 7

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

  • A. Information management systems
  • B. Work performance reports
  • C. Stakeholder analysis
  • D. Data gathering and representation

Answer: A

NEW QUESTION 8

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

  • A. quality.
  • B. value.
  • C. technical performance.
  • D. statu

Answer: B

NEW QUESTION 9

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

  • A. Monitoring and Controlling
  • B. Initiating
  • C. Planning
  • D. Executing

Answer: A

NEW QUESTION 10

What is a tool to improve team performance?

  • A. Staffing plan
  • B. External feedback
  • C. Performance reports
  • D. Co-location

Answer: D

NEW QUESTION 11

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

  • A. Activity network diagrams
  • B. Affinity diagrams
  • C. Matrix diagrams
  • D. Interrelationship digraphs

Answer: B

NEW QUESTION 12

Cost baseline is an output of which of the following processes?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Estimate Activity Resources

Answer: B

NEW QUESTION 13

When can pre-assignment of project team members occur?

  • A. When the project uses capital expenditures
  • B. When the required staff can be acquired from outside sources
  • C. When the project would be ignored due to travel expenses
  • D. When the project is the result of specific people being promised as part of a competitive proposal

Answer: D

NEW QUESTION 14

A regression line is used to estimate:

  • A. Whether or not a process is stable or has predictable performance.
  • B. How a change to the independent variable influences the value of the dependent variable.
  • C. The upper and lower specification limits on a control chart.
  • D. The central tendency, dispersion, and shape of a statistical distributio

Answer: B

NEW QUESTION 15

Which Control Quality tool is also known as an arrow diagram?

  • A. Matrix diagram
  • B. Affinity diagram
  • C. Tree diagram
  • D. Activity network diagram

Answer: D

NEW QUESTION 16

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

  • A. A risk urgency assessment.
  • B. The scope baseline.
  • C. Work performance information.
  • D. Procurement audit

Answer: C

NEW QUESTION 17

An output of the Develop Project Team process is:

  • A. Organizational process assets.
  • B. Enterprise environmental factors updates.
  • C. Project staff assignments.
  • D. Organizational charts and position description

Answer: B

NEW QUESTION 18

In complex projects/ initiating processes should be completed:

  • A. Within a work package.
  • B. In each phase of the project.
  • C. To estimate schedule constraints.
  • D. To estimate resource allocation

Answer: B

NEW QUESTION 19

Which of the following is an output of Direct and Manage Project Execution?

  • A. Project management plan
  • B. Change request status updates
  • C. Organizational process assets updates
  • D. Work performance information

Answer: D

NEW QUESTION 20

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

  • A. Planning.
  • B. Executing,
  • C. Monitoring and Controlling.
  • D. Closin

Answer: C

NEW QUESTION 21
......

P.S. Easily pass CAPM Exam with 704 Q&As DumpSolutions.com Dumps & pdf Version, Welcome to Download the Newest DumpSolutions.com CAPM Dumps: https://www.dumpsolutions.com/CAPM-dumps/ (704 New Questions)