NEW QUESTION 1

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

  • A. Cost management plan
  • B. Quality management plan
  • C. Communications management plan
  • D. Risk management plan

Answer: D

NEW QUESTION 2

Which document in the project management plan can be updated in the Plan Procurement Management process?

  • A. Budget estimates
  • B. Risk matrix
  • C. Requirements documentation
  • D. Procurement documents

Answer: C

NEW QUESTION 3

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

  • A. Project Risk Management
  • B. Project Human Resource Management
  • C. Project Scope Management
  • D. Project Stakeholder Management

Answer: D

NEW QUESTION 4

What is the responsibility of the project manager and the functional manager respectively?

  • A. Oversight for an administrative area; a facet of the core business
  • B. Achieving the project objectives; providing management oversight for an administrative area
  • C. A facet of the core business; achieving the project objectives
  • D. Both are responsible for achieving the project objective

Answer: B

NEW QUESTION 5

Which input will be used when tasked with developing the human resource plan?

  • A. Project management plan
  • B. Activity resource requirements
  • C. Resource calendar
  • D. Project staff assignments

Answer: B

NEW QUESTION 6

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

  • A. Teaming
  • B. Collective bargaining
  • C. Sharing
  • D. Working

Answer: A

NEW QUESTION 7

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

  • A. Cost-reimbursable
  • B. Time and material
  • C. Fixed price or lump-sum
  • D. Cost-plus-fixed-fee

Answer: C

NEW QUESTION 8

Which grid shows which resources are tied to work packages?

  • A. Work breakdown structure (WBS)
  • B. Responsibility assignment matrix (RAM)
  • C. Project assignment chart
  • D. Personnel assignment matrix

Answer: B

NEW QUESTION 9

During which process group is the quality policy determined?

  • A. Initiating
  • B. Executing
  • C. Planning
  • D. Controlling

Answer: C

NEW QUESTION 10

Which tool or technique is used to manage change requests and the resulting decisions?

  • A. Change control tools
  • B. Expert judgment
  • C. Delphi technique
  • D. Change log

Answer: A

NEW QUESTION 11

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

  • A. Schedule
  • B. Quality
  • C. Communications
  • D. Cost

Answer: C

NEW QUESTION 12

Which of the following is an output of Define Scope?

  • A. Project scope statement
  • B. Project charter
  • C. Project plan
  • D. Project schedule

Answer: A

NEW QUESTION 13

An input to the Collect Requirements process is the:

  • A. stakeholder register.
  • B. project management plan.
  • C. project scope statement.
  • D. requirements management pla

Answer: A

NEW QUESTION 14

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

  • A. Performing
  • B. Storming
  • C. Norming
  • D. Forming

Answer: C

NEW QUESTION 15

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

  • A. scope creep.
  • B. a change request.
  • C. work performance information.
  • D. deliverable

Answer: A

NEW QUESTION 16

What is the definition of Direct and Manage Project Execution?

  • A. Integrating all planned activities
  • B. Performing the activities included in the plan
  • C. Developing and maintaining the plan
  • D. Execution of deliverables

Answer: B

NEW QUESTION 17

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

  • A. Decomposition
  • B. Benchmarking
  • C. Inspection
  • D. Checklist analysis

Answer: C

NEW QUESTION 18

Which of the following is an example of the simplest fixed-price contract?

  • A. Purchase requisition
  • B. Purchase order
  • C. Verbal agreement
  • D. Request for quote

Answer: B

NEW QUESTION 19

An input to Develop Project Charter is a/an:

  • A. Business case.
  • B. Activity list.
  • C. Project management plan.
  • D. Cost forecas

Answer: A

NEW QUESTION 20

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

  • A. Three weeks
  • B. Four weeks
  • C. Five weeks
  • D. Six weeks

Answer: C

NEW QUESTION 21
......

P.S. Easily pass CAPM Exam with 704 Q&As Dumps-files.com Dumps & pdf Version, Welcome to Download the Newest Dumps-files.com CAPM Dumps: https://www.dumps-files.com/files/CAPM/ (704 New Questions)