NEW QUESTION 1
Lessons learned are created and project resources are released in which Process Group?
Answer: C
NEW QUESTION 2
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
Answer: B
NEW QUESTION 3
Which activity may occur at project or phase closure?
Answer: A
NEW QUESTION 4
What is project management?
Answer: B
NEW QUESTION 5
Which activity is an input to the Conduct Procurements process?
Answer: A
NEW QUESTION 6
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
Answer: B
NEW QUESTION 7
Which of the following is an output of the Monitor and Control Project Work process?
Answer: A
NEW QUESTION 8
The completion of the project scope is measured against the:
Answer: C
NEW QUESTION 9
Plan-do-check-act is also known as:
Answer: D
NEW QUESTION 10
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
Answer: B
NEW QUESTION 11
Which of the following strategic considerations often results in project authorization?
Answer: D
NEW QUESTION 12
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Answer: C
NEW QUESTION 13
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Answer: A
NEW QUESTION 14
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
Answer: D
NEW QUESTION 15
A project manager builds consensus and overcomes obstacles by employing which communication technique?
Answer: B
NEW QUESTION 16
The procurement process that documents agreements and related documentation for future reference is known as:
Answer: C
NEW QUESTION 17
Which technique is used in Perform Quantitative Risk Analysis?
Answer: A
NEW QUESTION 18
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
Answer: C
NEW QUESTION 19
Which item is a cost of conformance?
Answer: A
NEW QUESTION 20
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Answer: A