Master the PMP Project Management Professional content and be ready for exam day success quickly with this Passleader PMP free exam. We guarantee it!We make it a reality and give you real PMP questions in our PMP PMP braindumps.Latest 100% VALID PMP PMP Exam Questions Dumps at below page. You can use our PMP PMP braindumps and pass your exam.
Also have PMP free dumps questions for you:
NEW QUESTION 1
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Answer: C
NEW QUESTION 2
Which of the following is an example of a technique used in quantitative risk analysis?
Answer: A
NEW QUESTION 3
Which project document is updated in the Control Stakeholder Engagement process?
Answer: B
NEW QUESTION 4
An input to the Perform Quantitative Risk Analysis process is the:
Answer: D
NEW QUESTION 5
For a stakeholder with low interest and high power, the project manager should:
Answer: C
NEW QUESTION 6
The process of developing a detailed description of the project and product is known as:
Answer: D
NEW QUESTION 7
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Answer: B
NEW QUESTION 8
Technical capability, past performance, and intellectual property rights are examples of:
Answer: B
NEW QUESTION 9
Which process requires implementation of approved changes?
Answer: A
NEW QUESTION 10
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
Answer: C
NEW QUESTION 11
Which type of analysis would be used for the Plan Quality process?
Answer: D
NEW QUESTION 12
Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?
Answer: D
NEW QUESTION 13
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Answer: D
NEW QUESTION 14
Which schedule network analysis technique modifies the project schedule to account for limited resources?
Answer: C
NEW QUESTION 15
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
Answer: A
NEW QUESTION 16
The diagram below is an example of a:
Answer: A
NEW QUESTION 17
Which tool and technique of quality planning involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
Answer: C
NEW QUESTION 18
Which input to the Plan Risk Management process provides information on high-level risks?
Answer: A
NEW QUESTION 19
What is the minimum a project schedule must include?
Answer: B
NEW QUESTION 20
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Answer: A
NEW QUESTION 21
Another name for an Ishikawa diagram is:
Answer: A