Testking offers free demo for PMP exam. "Project Management Professional", also known as PMP exam, is a PMP Certification. This set of posts, Passing the PMP PMP exam, will help you answer those questions. The PMP Questions & Answers covers all the knowledge points of the real exam. 100% real PMP PMP exams and revised by experts!

Online PMP PMP free dumps demo Below:

NEW QUESTION 1

During which process does the project team receive bids and proposals?

  • A. Conduct Procurements
  • B. Plan Procurements
  • C. Estimate Costs
  • D. Control Budget

Answer: A

NEW QUESTION 2

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

  • A. ends.
  • B. begins.
  • C. delays.
  • D. deviates.

Answer: A

NEW QUESTION 3

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

  • A. Benchmarking.
  • B. Context diagrams.
  • C. Brainstorming.
  • D. Prototyping.

Answer: D

NEW QUESTION 4

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

  • A. portfolio
  • B. program
  • C. selection
  • D. sub portfolio

Answer: B

NEW QUESTION 5

Which of the following is an output of Direct and Manage Project Execution?

  • A. Project management plan
  • B. Change request status updates
  • C. Organizational process assets updates
  • D. Work performance information

Answer: D

NEW QUESTION 6

A tool and technique used in the Develop Project Charter process is:

  • A. change control tools
  • B. expert judgment
  • C. meetings
  • D. analytical techniques

Answer: B

NEW QUESTION 7

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

  • A. Perform Quality Control
  • B. Quality Policy
  • C. Perform Quality Assurance
  • D. Quality Planning

Answer: C

NEW QUESTION 8

How is scheduled variance calculated using the earned value technique?

  • A. EV less AC
  • B. AC less PV
  • C. EV less PV
  • D. AC less EV

Answer: C

NEW QUESTION 9

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

  • A. Start-to-start (SS).
  • B. Start-to-finish (SF).
  • C. Finish-to-start (FS).
  • D. Finish-to-finish (FF).

Answer: C

NEW QUESTION 10

Which of the following is contained within the communications management plan?

  • A. An organizational chart
  • B. Glossary of common terminology
  • C. Organizational process assets
  • D. Enterprise environmental factors

Answer: B

NEW QUESTION 11

Which tool and technique is used in Conduct Procurements?

  • A. Teaming agreements
  • B. Expert judgment
  • C. Bidder conferences
  • D. Contract types

Answer: C

NEW QUESTION 12

Documented identification of a flaw in a project component together with a recommendation is termed a:

  • A. corrective action.
  • B. preventive action.
  • C. non-conformance report,
  • D. defect repair.

Answer: D

NEW QUESTION 13

Which process numerically analyzes the effect of identified risks on overall project objectives?

  • A. Plan Risk Management
  • B. Plan Risk Responses
  • C. Perform Quantitative Risk Analysis
  • D. Perform Qualitative Risk Analysis

Answer: C

NEW QUESTION 14

The project scope statement and resource calendars are inputs to which Project Time Management process?

  • A. Sequence Activities
  • B. Estimate Activity Resources
  • C. Develop Schedule
  • D. Control Schedule

Answer: C

NEW QUESTION 15

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

  • A. Bottom-up
  • B. Parametric
  • C. Analogous
  • D. Three-point

Answer: A

NEW QUESTION 16

Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?

  • A. Gantt chart
  • B. Project schedule network diagram
  • C. Project milestone list
  • D. Activity list

Answer: B

NEW QUESTION 17

Which of the following procurement processes results in the awarding of a procurement contract?

  • A. Administer Procurements
  • B. Close Procurements
  • C. Conduct Procurements
  • D. Plan Procurements

Answer: C

NEW QUESTION 18

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

  • A. a Knowledge Area
  • B. a Process Group
  • C. program management
  • D. portfolio management

Answer: A

NEW QUESTION 19

Projects are separated into phases or subprojects; these phases include:

  • A. feasibility study, concept development, design, and prototype.
  • B. initiate, plan, execute, and monitor.
  • C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
  • D. Identify Stakeholders, develop concept, build, and test.

Answer: A

NEW QUESTION 20

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

  • A. Efficient
  • B. Effective
  • C. Push
  • D. Pull

Answer: B

NEW QUESTION 21

In the Initiating Process Group, at what point does the project become officially authorized?

  • A. When the project charter is signed
  • B. When all the stakeholders agree on the scope of the project
  • C. When the project manager is appointed
  • D. When the necessary finance or funding is obtained

Answer: A