Testking offers free demo for PMP exam. "Project Management Professional", also known as PMP exam, is a PMP Certification. This set of posts, Passing the PMP PMP exam, will help you answer those questions. The PMP Questions & Answers covers all the knowledge points of the real exam. 100% real PMP PMP exams and revised by experts!
Online PMP PMP free dumps demo Below:
NEW QUESTION 1
During which process does the project team receive bids and proposals?
Answer: A
NEW QUESTION 2
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
Answer: A
NEW QUESTION 3
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Answer: D
NEW QUESTION 4
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
Answer: B
NEW QUESTION 5
Which of the following is an output of Direct and Manage Project Execution?
Answer: D
NEW QUESTION 6
A tool and technique used in the Develop Project Charter process is:
Answer: B
NEW QUESTION 7
Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?
Answer: C
NEW QUESTION 8
How is scheduled variance calculated using the earned value technique?
Answer: C
NEW QUESTION 9
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Answer: C
NEW QUESTION 10
Which of the following is contained within the communications management plan?
Answer: B
NEW QUESTION 11
Which tool and technique is used in Conduct Procurements?
Answer: C
NEW QUESTION 12
Documented identification of a flaw in a project component together with a recommendation is termed a:
Answer: D
NEW QUESTION 13
Which process numerically analyzes the effect of identified risks on overall project objectives?
Answer: C
NEW QUESTION 14
The project scope statement and resource calendars are inputs to which Project Time Management process?
Answer: C
NEW QUESTION 15
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Answer: A
NEW QUESTION 16
Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?
Answer: B
NEW QUESTION 17
Which of the following procurement processes results in the awarding of a procurement contract?
Answer: C
NEW QUESTION 18
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
Answer: A
NEW QUESTION 19
Projects are separated into phases or subprojects; these phases include:
Answer: A
NEW QUESTION 20
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
Answer: B
NEW QUESTION 21
In the Initiating Process Group, at what point does the project become officially authorized?
Answer: A