Want to know Testking 70-499 Exam practice test features? Want to lear more about Microsoft Recertification for MCSD: Application Lifecycle Management certification experience? Study Certified Microsoft 70-499 answers to Most recent 70-499 questions at Testking. Gat a success with an absolute guarantee to pass Microsoft 70-499 (Recertification for MCSD: Application Lifecycle Management) test on your first attempt.

2021 Aug 70-499 test question

Q101. - (Topic 2) 

You are a test developer using Microsoft Test Manager (MTM). 

You are developing a test case that must be run multiple times with different input values for a specific field each time. You have a list of values that will be used for the input. 

You need to modify the test to enter each value into the field. 

What should you do? 

A. Insert a parameter into the Action column of the test step and enter the input values into the Parameter Values pane. 

B. Insert a parameter into the Expected Results column of the test step and enter the input values into Parameter values pane. 

C. Insert a parameter into the Action column of the test step. 

D. Create test steps for each input value in the Action column. 

Answer: A 


Q102. - (Topic 1) 

You have upgraded an installation of Microsoft Visual Studio Team Foundation Server (TFS) 2013. 

You need to modify an existing project on which you want to enable portfolio management. 

What should you do? 

A. Update the application tier. 

B. Move team projects to a project collection. 

C. Update team projects with Team Explorer. 

D. Run the Configure Features wizard. 

Answer: D 

Explanation: http://msdn.microsoft.com/en-us/library/ff432837.aspx 


Q103. - (Topic 1) 

Your network environment is configured according to the following table: 

TFS2 experiences complete hardware failure. 

You need to replace TFS2. 

You install TFS on a new server. In which mode should you configure TFS? 

A. Upgrade 

B. Application-Tier only 

C. Advanced 

D. Basic 

Answer: B 


Q104. - (Topic 3) 

You are developing an application by using a team of developers and a team of testers. You have an automated nightly build. 

Currently, the testers take too long to test and the developers are closing a large number of bugs as “unable to reproduce.” 

You need to improve the test cycle time. 

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.) 

A. Enable code analysis. 

B. Instruct the testers to use diagnostic data collection in their test environment. 

C. Instruct the testers to test only every other build. 

D. Instruct the testers to use action recordings and playback during manual testing. 

E. Assign an extra day for testing at the end of the iteration. 

Answer: B,D 


Q105. - (Topic 3) 

Your company is developing a new version of an existing application. The current list of feature requests is made up mostly of three years’ worth of bug reports and help desk support call data. 

The company has no formal process for requesting input from its customer base. 

You need to be able to prioritize the information and develop an accurate, useful list of feature requests. 

What are three possible ways to accomplish this goal? (Each correct answer presents a complete solution. Choose three.) 

A. 

Use focused customer interviews to review the bug reports and help desk data. 

Create the requirements documents from the resulting information. 

B. 

Create a single requirements document that includes all the bug reports and help desk call items. 

Put this document on the backlog of the project. 

C. 

Working from the bug reports and help desk data, create an Excel workbook project matrix that ranks items based on complexity and priority. 

Determine the project requirements for the next iteration that includes the top ranking items on the matrix. 

D. 

use storyboarding diagrams and work with the stakeholders to filter, map, and expand on the bug reports and help desk call data. 

Review the diagrams with the stakeholders and create requirements documents based on that review. 

E. 

Hold a series of joint application design (JAD) sessions with representation from support, 

development, help desk, and customers. Filter out the bad items from the bug reports and help desk data. 

Create formal requirements documents based on the results of these sessions. 

Answer: B,C,E 


70-499 test questions

Rebirth 70-499 actual test:

Q106. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server. 

Version control is configured with one project collection and two team projects. Some users use 2010 and 2012 clients, such as Visual Studio and Team Explorer Everywhere. 

You need to ensure that users will be prompted by, and can satisfy, the comments check-in policy when using both 2010 and 2012 clients. 

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.) 

A. Add the Changeset Comments policy in the team project collection’s source control settings. 

B. Add the Changeset Comments policy in the source control settings for each team project. 

C. Install the TFS 2010 Power Tools on all clients. 

D. Install the TFS 2012 Power Tools on all clients and configure the policy by using Team Explorer. 

E. Install the TFS 2010 and 2012 Power Tools on the TFS application tier and configure the policy by using Team Foundation Administrator. 

Answer: B,C 


Q107. - (Topic 3) 

You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently 

finished a sprint. 

You need to conduct a retrospective meeting prior to planning the next sprint. 

What should you do? 

A. Select items from the product backlog for the next sprint. 

B. Decompose the product backlog items into a set of tasks. 

C. Determine which items have been finished on the previous day. 

D. Analyze the previous sprint to identify what the team is going to do differently during the next sprint. 

Answer: D 

Explanation: This meeting provides an opportunity for the Scrum Team to inspect themselves and identify what went well and what needs improving. If improvements are identified, the team should create an actionable plan for the next Sprint. Nothing is out of scope during this meeting—people, relationships, process, and tools can all be discussed. The Scrum Team may also decide to adjust its Definition of “Done” to increase product quality. After the meeting, the next Sprint begins. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.6 


Q108. - (Topic 3) 

Your development team uses Scrum as its process framework and utilizes the Microsoft Framework (MSF) for Agile Software Development 6.0 process template. 

A new team member who is new to Scrum assumes the role of product owner. 

You need to help the new product owner prioritize the product backlog. 

Which basis should you suggest the new product owner use for prioritizing the product backlog? 

A. personal preference 

B. estimated cost and effort for each requirement 

C. risk and business value of each requirement 

D. technical complexity of each requirement 

Answer: C 

Explanation: In other words, it’s more important to deliver business value in the form of working software than to follow a plan. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.162 


Q109. - (Topic 3) 

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. 

The team has identified items from the product backlog for the next sprint. 

You need to ensure that the team has adequate capacity to complete the next sprint. 

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.) 

A. Review the sprint Burndown chart. 

B. Have the team assign hour estimates to each sprint task. 

C. Review the sprint backlog. 

D. Assign story points to each item in the product backlog. 

E. Review the product backlog with forecast set to On to determine if the sprint can be completed based on the team’s velocity. 

F. Set each team member’s per day capacity. 

Answer: C,E,F 

Explanation: Sprint Burndown charts can show the team how much work remains in the Sprint. These charts will often include an ideal trend line. This line represents the ideal rate at which the Development Team is able to complete all of the remaining effort, at a constant rate, by the end of the Sprint. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.283 

Prior to the Sprint, there shouldn’t be any Task work items in the Sprint Backlog. Ideally, the Development Team creates its tasks during the Sprint Planning meeting and not before. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.175 

The Sprint Backlog contains those items selected by the Development Team plus a plan for delivering them. The Sprint Backlog shows the work remaining in the Sprint at all times. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.4 

Story points should be already assigned to PBIs during identification for the sprint. 


Q110. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server. 

You build a multi-tiered application that contains the following tiers: 

.... 

User Interface Application Services Integration Services Database 

You need to modify the item template to meet the following requirements: 

.. 

When a bug is created, the testing team is able to identify the application tier. You are able to produce a report of bugs by tier. 

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.) 

A. Add a control to the work item FORM. For type, select WorkltemClassificationControl. 

B. Add a new FIELD called Custom.ApplicationTier Application Tier and configure its list of ALLOWEDVALUES LISTITEMS to be: 

User Interface 

Application Services 

Integration Services 

Database 

C. 

Add a control to the work item FORM. For type, select FieldControl. 

D. 

Add the attribute reportable^Dimension to the FIELD definition. 

E. 

Add the attribute reportable = Measure to FIELD definition. 

Answer: A,B,C